JUNE 2024 - QUARTERLY ACTIVITIES REPORT
KEY POINTS
Ironstone Well-Barwidgee
•
During the quarter, an RC drilling program comprising 33 holes for 4,688m (inclusive of
pre-collars) was completed at the Oblique and Quarter Moon prospects within the
Ironstone Well-Barwidgee Project, 50km south of the Jundee gold operation (ASX:
NST). All assay results were received and reported.
•
At Oblique, the results confirmed the continuity of broad and higher-grade
mineralisation and extended mineralisation 150m to the north with intercepts
including:
o
15m @ 1.7g/t from 74m (24IWBRC0002)
o
•
28m @ 1.1 g/t Au from 50m (24IWBRC0012),
including 4m @ 3.3g/t Au from 51m and
4m @ 2.1g/t Au from 71m
At Quarter Moon, results indicate the presence of multiple high-grade cross-cutting
zones of mineralisation within intercepts, including:
6m @ 4.2 g/t Au from 90m (24IWBRC0032),
including 1m @ 21.2g/t Au from 94m,
6m @ 3.2/t Au from 143m (24IWBRC0032),
including 1m @ 13.1g/t Au from 147m
2m @ 6.3/t Au from 99m (24IWBRC0028),
•
including 3m @ 5.3g/t Au from 79m
including 1m @ 12.1g/t Au from 99m
A ~2,800m (exclusive of pre-collars) diamond drilling program commenced in May
testing depth extents and structural controls at Oblique, Quarter Moon and New
England Granite prospects. No diamond drilling assay results had been received at
Quarters end.
Corporate
•
Approx. $5.8m in cash and cash equivalents available at the end of the Quarter.
For further information or to ask questions in relation to this announcement, please visit our
Investor Hub at https://investorhub.yandalresources.com.au/link/XyOMdr
Contact Us
A: Level 1 Unit 5/62 Ord Street,
West Perth WA 6005
T: +61 (0)8 9389 9021
E: yandal@yandalresources.com.au
yandalresources.com.au | ASX:YRL
Board and Management
Chris Oorschot
Managing Director/CEO
Greg Evans
Non-Executive Chair
Katina Law
Non-Executive Director
Tim Kennedy
Executive Director
Greg Fitzgerald
Company Secretary
Yandal Resources Ltd (ASX: YRL, “Yandal Resources” or the “Company”) is pleased to provide a
summary of operational and corporate activities undertaken during the quarter ended 30 June
2024.
The Company remains focused on exploring its portfolio of highly prospective 100% owned gold
projects located in the Yandal and Norseman-Wiluna Greenstone Belts in Western Australia
(Figure 1).
Figure 1: Yandal Resources’ gold project locations.
June Quarter Operational Summary and 2024 Outlook
During the June Quarter, the Company concentrated its exploration efforts on advanced
prospects within the Ironstone Well–Barwidgee Project (IWB) in the northern Yandal Belt. Drilling
activities significantly ramped up with the completion of RC drilling across the Oblique and
Quarter Moon Prospects and the commencement of diamond drilling.
The Company acquired new regional datasets which resulted in the successful delineation of
several large-scale gold exploration targets, highlighting the significant under-explored
exploration potential across the project. It is intended to advance these exciting new prospects
to drill testing stage in the 2nd half of 2024. Additionally, follow-up drilling programs will be
planned once results from the recently completed RC and diamond drilling programs at IWB
have been received and interpreted.
yandalresources.com.au | ASX:YRL
2
IRONSTONE
WELLBARWIDGEE
The 100% owned IWB Gold
Project
covers
approximately
370km²
highly prospective and
under-explored
tenure
located
between
the
Jundee and Bronzewing
mines in the northern
Yandal Greenstone Belt
(Figure2).
Yandal has an established
Resource of 268,000oz of
gold at Flushing Meadows
and considers there to be
strong potential to make
new
discoveries
and
expand this resource base
within its’ extensive tenure
holding. Refer to the ASX
announcement
of
4
November 2020 for details
of the Flushing Meadows
Resource.
The project area has
several prospects where
limited historic and YRL
drilling has returned robust
gold intercepts, indicating
Figure 2: Ironstone Well / Barwidgee Project Overview showing the
the potential for large
outline of YRL tenure, regional interpreted bedrock geology, and the
scale discoveries which
location of prospects discussed in this report.
are the focus of ongoing
exploration. These prospects include Quarter Moon and Oblique, which together with the
nearby Flushing Meadows deposit, have the potential to develop into a gold “camp” as well
as the earlier stage New England Granite towards the southern end of the project.
yandalresources.com.au | ASX:YRL
3
Drilling Program
An RC program commenced in March was completed during the June Quarter for a total of
33 holes (4,688m) testing the Oblique and Quarter Moon Prospects. Detailed results for
Oblique were released on 29 April and 18 June 2024 and results for Quarter Moon were
released on 3 July 2024.
A diamond drilling program comprising 10 holes (~2,800m) commenced in May testing
depth and strike extents of mineralisation at Oblique (5 holes) and Quarter Moon (3 holes)
and proving structural and geological information ahead of a larger RC program at New
England Granite (part funded by GSWA EIS scheme). At quarters end diamond drilling had
been completed at Oblique and was nearing completion at Quarter Moon, however no
assay results had been received.
Oblique RC Drilling Results
The Oblique RC program comprised 2,450m of drilling for a total of 18 holes (including five
diamond pre-collars with 516m drilled). The holes were designed to identify OBL01 parallel
structures to the north, then test the continuity and extend drilling within the OBL01
mineralised structure (see Figures 3 & 4). RC drilling was successful in achieving both
objectives.
Drilling to the north of Oblique has confirmed an OBL01-like structure up to 650m from any
previous drilling completed by the Company. Notable intercepts include:
•
15m @ 1.7 g/t Au from 74m in 24IWBRC0002
o
including 3m @ 5.3g/t Au from 79m
•
7m @ 0.9 g/t Au from 47m in 24IWBRC0018 and
•
3m @ 1.4 g/t Au from 73m in 24IWBRC0018
These results suggest that mineralisation is associated with a dextral offset in stratigraphy
(based on historic surface mapping) and the core of the large-scale magnetic anomaly
coincident with the prospect.
RC drilling within and to the south of the OBL01 structure resulted in several intercepts,
including:
•
28m @ 1.1 g/t Au from 50m in 24IWBRC0012
o
o
including 4m @ 3.3g/t Au from 51m and
4m @ 2.1g/t Au from 71m
This result extends oxide mineralisation 50m south of the previously reported:
•
24m @ 1.8g/t Au from 60m in YRLRC1177 (previously reported on the 12tt of January 2024)
yandalresources.com.au | ASX:YRL
4
Results including:
•
9m @ 1.8/t Au from 34m in 24IWBRC0011
o
including 1m @ 10.2g/t Au from 34m
•
7m @ 0.8g/t Au from 20m, and
•
4m @ 1.3g/t Au from 76m in 24IWBRC0011 (a vertical hole)
confirm mineralisation continuity within the interpreted OBL01 structure, which is associated with
a wide interval of oxidised and deformed quartz veining and/or microcrystalline chert with
evidence of strong alteration, including sulphide alteration (now oxidised).
Once the diamond drilling phase of the program testing the broader mineralised system at
Oblique has been completed, our mineralisation model for the prospect will be updated,
and further testing will be planned.
Figure 3: A Collar plan for the Oblique Prospect displaying all drilling collars, colour-coded by max
Au in hole (g/t Au), overlying a composite aerial magnetic image e (RTP 1VD non-linear and RTP
yandalresources.com.au | ASX:YRL
5
2VD non-linear). Collar ID’s for intercepts required Diamond pre-collars and section/longitudinal
section positions are labelled.
Figure 4: Longitudinal section, southwest facing, showing intercepts within the OBL01 structure and
thematically contoured by grade (g/t Au) multiplied by down-hole width (m). The planned position of
diamond hole pierce points within the OBL01 structure are also shown.
Quarter Moon RC Drilling Results
The Quarter Moon RC program comprised 2,238m of drilling for 15 holes (including three
diamond pre-collars with 306m drilled). The holes were designed to provide insights into the
geometry of mineralisation across the primary mineralised trend hosted within a fractionated
dolerite and to test footwall regolith anomalies over a parallel mafic body to the west.
Significant intercepts are summarised below and illustrated in Figure 5
Closer-spaced drilling on several 50-metre-spaced sections adjacent to previous or historic
intercepts has successfully confirmed the presence of high-grade mineralisation,
demonstrated mineralisation continuity and suggests that high-grade mineralisation is
controlled by structures cross-cutting the dolerite host unit.
yandalresources.com.au | ASX:YRL
6
Evidence of mineralisation continuity is seen in the south with:
•
2m @ 6.3 g/t Au from 99m in 24IWBRC0028
o
including 1m @ 12.1 g/t Au from 99m
This result is directly up-dip of the historic intercept,
•
9m @ 2.5 g/t Au from 140m in GCMQTMC6 (historic intercept),
o
Including 3m @ 5.6g/t Au from 143m
Combined with results from historic drilling to the north and south, these results suggest
mineralisation is striking approximately 300° and dipping 65° to the northeast. This revised
interpreted geometry is significant if dominant across the prospect, as:
•
Any mineralised structures intercepted in previous drilling would not have been tested
by drilling on the 100m spaced drilling lines to the north or south, as the structure would
dip below drilling on the adjacent line,
•
Any significant intercepts on the 100m spaced sections likely represent parallel
mineralised structures,
•
The historic drilling direction is not orthogonal to mineralisation,
•
Previous drilling has not effectively tested high-grade mineralisation strike or dip extent
within the dolerite host.
The current diamond drilling program across Quarter Moon will provide some verification of
this interpretation of mineralisation and further refine the geological model across the
Prospect.
350m to the north of 24IWBRC0028, RC results suggest there are multiple stacked high-grade
mineralised structures present with up to three high-grade zones intercepted within
24IWBRC0032:
•
•
•
8m @ 1.7 g/t Au from 43m (Figure 3)
o
Including 2m @ 5.0 g/t Au from 43m
o
Including 2m @ 11.9g/t Au from 94m
o
Including 1m @ 13.1 g/t Au from 147m
6m @ 4.2 g/t Au from 90m
6m @ 3.2 g/t Au from 143m
Exploration RC drilling targeting a footwall regolith anomaly identified low-level gold
anomalism but did not detect significant mineralisation.
yandalresources.com.au | ASX:YRL
7
Diamond Drilling
Diamond drilling commenced on May 24th at the Oblique Prospect and on June 23rd at
Quarter Moon. The diamond drilling underpins the Company’s strategy to understand the
broader potential of the Oblique and Quarter Moon mineralised systems. Five planned
diamond holes have been completed across Oblique, and two of three planned diamond
holes were completed at Quarter Moon during the Quarter. Oblique diamond drilling is
tested down to a maximum vertical depth of 400m, while Quarter Moon drilling is tested
down to a maximum vertical depth of 300m.
At Oblique, preliminary logging indicates that the stratigraphy is dominated by a bimodal
sequence of variably altered fine-grained andesite and an intermediate tuff characterised
by medium to coarse-grained volcanic laths.
Several different styles of structure and alteration have been observed, including:
• Altered and sulphide-bearing shear zones,
•
Deformed quartz veining,
•
Massive to semi-massive pyrite dominant sulfides typically adjacent to or containing
quartz veining and/or microcrystalline cherts. Equivalent sulphide alteration has been
observed in RC drilling previously and is typically correlated with low-level anomalous
gold values only.
At Quarter Moon, preliminary logging indicates a fractionated dolerite host with an actual
width of approximately 50-60m, cross-cut narrow 0.5-5m wide shear zones hosting quartz
veins and strong silica-pyrite alteration.
yandalresources.com.au | ASX:YRL
8
Figure 5: A Collar plan for the Quarter Moon Prospect displays all drilling collars, colour-coded by max Au
in hole (g/t Au), overlying a composite aerial magnetic image (RTP 1VD non-linear and RTP 2VD non-linear).
Diamond pre-collars and cross-section positions are labelled. The surface projection of the interpreted
strike of mineralisation is also plotted.
yandalresources.com.au | ASX:YRL
9
Ground Gravity Survey and New Large-Scale Targets
A ground gravity survey commenced in late March was completed during the quarter across
the northeastern half of the IWB Project and a smaller area around the New England Granite
Prospect . The survey comprised 2,288 200m spaced stations across 67 200m spaced northsouth lines, with 148 repeat observations for quality control. Survey parameters and results
were reported in detail on 11 June 2024.
A key outcome of the survey was the identification of several early-stage but high potential
conceptual targets.
These conceptual targets (see Figure 6 for locations) include:
•
Target A: The truncated large-scale fold in gravity Domain B, designated the Caladan Fold,
presents a conceptual litho-structural architecture comparable to several world-class gold
camps, such as the Kalgoorlie Gold Field (see Figure 7) in Norseman-Wiluna Greenstone
Belt of Western Australia*1 or the Timmins-Porcupine District in the Abitibi Greenstone Belt
of Canada*1 where three to eight kilometre scale folded mafic sequence is truncated by
sub-parallel or oblique (to fold axis) fault or shear. The entire feature is of interest.
•
Target B: A dolerite-basalt complex within Domain C, designated the Irulan Dolerite
Complex, presents a 7km long by 1km wide mafic block bracketed by a felsic to
intermediate volcaniclastic and sedimentary sequence to the east and west. The
Barwidgee Shear Zone is proximal to the western margin, and Structure A is to the east
margin. This conceptual target area shows similarities to the litho-structural setting of the
Jundee Deposits*1 65km to the north.
•
Target C: A broad 10° to 15° flexure in Structure A adjacent and 2.5km east of the 268koz
Flushing Meadows deposit coincides with the extrapolation of several late faults/shears.
This target area has been designated as the Giedi Prime target.
•
Target D: A subtle flexure in Structure B just above the Caladan Fold nose coincides with
the projection of several late structures. This target has been designated a Corrino target.
*1. These comparisons are conceptual in nature and are referenced to highlight a similarity in the broad litho-
structural setting only.
yandalresources.com.au | ASX:YRL
10
Giedi Prime
Target
Corrino
Target
Caladan
Fold
Oblique
C
Quarter
Moon
D
A
Flushing
Meadows
B
Irulan Dolerite
Complex
New England
Granite
Figure 6: Simplified bedrock geology interpretation with main features of the preliminary
ground gravity interpretation and existing Ironstone Well-Barwidgee Gold Project prospects
and targets.
yandalresources.com.au | ASX:YRL
11
Figure 7: A scale comparison between the interpreted Caladan Fold and the simplified
geology of the Kalgoorlie (A) and Timmins (B) District highlights the similarity in scale, geometry,
and structural setting of the conceptual target. Geology adapted from Fig. 9 from Phillips,
G.N., Groves, D.I., and Kerrich, R., 1996. Factors in the formation of the giant Kalgoorlie gold
deposit. Ore Geology Reviews, 10(3-6), pp.295-317.
yandalresources.com.au | ASX:YRL
12
Soil Sampling
Following a successful orientation soil program across selected areas of the IWB Project in
the December 2023 quarter, a large-scale follow-up soil program commenced in March
2024 and was completed in the June 2024 quarter. The program comprised approximately
1800 samples on a 400m x 200m spaced grid across much of the northern part of the project
(refer to ASX Announcement 26 February 2024). This work will result in a consistent and
comprehensive geochemical dataset across a significant portion of IWB and will assist in
ongoing targeting for gold, lithium and other commodities. Initial results from the soil sampling
program are expected in August 2024.
GORDONS
The Gordons Project is located 30km north of Kalgoorlie and 15km north of the Kanowna
Belle Gold Mine (ASX: NST), close to mill and haulage infrastructure (Figure 1).
The Project tenements straddle the eastern flank of the Scoti-Kanowna Dome, a geological
feature that is a regional control on mineralisation including the multi-million ounce Kanowna
Belle and Paddington gold mines
In mid-2023 the Company acquired exploration licence E27/701 (in application) abutting the
southern boundary of the project. This acquisition was in response to a 3D-structural study
which interpreted an important structural corridor (the Gordon Sirdar Shear Zone or “GSSZ”)
passing through the eastern portion of Yandal’s tenure, beyond which it extended south in
close proximity to the Gordon Sirdar Mine and then through E27/701.
Yandal has completed a target generation exercise over the GSSZ and has plans to drill test
these once E27/701 has been granted and access is finalised.
Soil Sampling
A soil sampling program was completed over the eastern half of the Gordons Project. The
program aimed to build a comprehensive surface geochemical dataset that can be
interrogated to aid in exploration targeting, focusing on emerging targets in the south of the
Project. The program comprised collection of 1,971 100m spaced samples on 400m spaced
lines across selected under explored areas of the Project. Initial results from the soil sampling
program are expected in July-August 2024.
LOOKING AHEAD
The Company has approximately $5.8m available at Quarters end and has a very active H2
CY 2024 planned with priority exploration activities, including;
yandalresources.com.au | ASX:YRL
13
1.
The initial analysis and interpretations of regional soil sampling results at IWB;
2.
Reporting of first results from the Oblique diamond drilling program expected in July;
3.
The completion of diamond drilling at Quarter Moon, with initial assay results expected
in August;
4.
The diamond drilling at the New England Granite Prospect;
5.
An assessment of historical exploration work across the recently identified conceptual
targets, including the Caladan Fold and Irulan Dolerite Complex, derived from the 2024
ground gravity survey across the Ironstone Well-Barwidgee Gold Project, is underway
(see ASX announcement dated 11 June 2024).
CORPORATE SUMMARY
Issued Capital
There were no movements in securities on issue during the quarter and as at 30 June 2024,
the Company had the following securities on issue:
Type of Security
30 June 2024
31 March 2024
Ordinary shares
267,807,614
267,807,614
Options
76,466,071
76,466,071
375,000
375,000
344,648,685
344,648,685
Performance rights
TOTAL
Summary of Exploration Expenditure
In accordance with Listing Rule 5.3.1, Yandal confirms that as disclosed in the Cashflow
Report (item 1.2(a)), Yandal’s exploration expenditure for the quarter was approximately
$1,310k, details of the exploration activities underlying this expenditure are as set out in the
Activities Report.
Payments to Related Parties and their Associates
In accordance with ASX Listing Rule 5.3.5, $174k was paid to related parties or their associates
during the quarter, comprising Executive Director salaries, Non-executive Director fees and
superannuation.
Authorised by the board of Yandal Resources
For further information, please contact:
Chris Oorschot
Managing Director
Yandal Resources Limited
yandal@yandalresources.com.au
yandalresources.com.au | ASX:YRL
Greg Fitzgerald
Company Secretary
+61 8 9389 9021
yandal@yandalresources.com.au
14
About Yandal Resources Limited
Yandal Resources was listed on the ASX in December 2018 and has a portfolio of advanced gold
exploration projects in the highly prospective Yandal and Norseman-Wiluna Greenstone Belts of Western
Australia.
Yandal Resources Ltd - Mineral Resource Summary
Indicated
Inferred
Deposit
Tonnes Grade
Au
Tonnes
Grade
Au
(‘000s)
(g/t)
(oz)
(‘000)
(g/t)
(oz)
Ironstone Well
Flushing Meadows1
2,141
1.3
91,000
5,245
1.1
177,000
Mt McClure
Challenger2
718
1.9
44,000
3
Success
1,255
1.9
75,000
Parmelia4
252
2.1
17,000
5
HMS Sulphur
1010
1.2
39,000
6
Gilmore
134
1.7
7,200
Sub-total - MMC
3,369
1.7
182,200
Gordons
Gordons Dam7
365
1.7
20,000
8
2,141
Grand-total
8,979
1.3
379,200
1.3
91,000
Total
Tonnes
(000’s)
Grade
(g/t)
Au
(Oz)
7,386
1.1
268,000
718
1.9
44,000
1,255
1.9
75,000
252
2.1
17,000
1010
1.2
39,000
134
3,369
1.7
1.7
7,200
182,200
365
1.7
20,000
11,120
1.4
470,200
Due to the effects of rounding, totals may not represent the sum of the individual
components.
1. Reported above 0.5g/t Au lower cut-off grade; refer to Yandal Resources Ltd ASX announcement dated 4 November
2020 for full details. 2. Reported above 1.0g/t Au lower cut-off grade; refer to Yandal Resources Ltd ASX announcement
dated 22 August 2022 for full details 3. Reported above 1.0g/t Au lower cut-off grade; refer to Yandal Resources Ltd ASX
announcement dated 6 September 2022 for full details.4. Reported above 1.0g/t Au lower cut-off grade; refer to Yandal
Resources Ltd ASX announcement dated 20 September 2022 for full details 5. Reported above 0.5g/t Au lower cut-off
grade within this announcement 6. Reported above 1.0g/t Au lower cut-off grade within this announcement 7. Reported
above 1.0g/t Au lower cut-off grade; refer to Yandal Resources Ltd ASX announcement dated 6 April 2023 for full details
8. All Resources are reported as global estimates, not constrained by optimised pit shells.
Competent Person Statement
The information in this document related to Exploration Targets and Exploration Results, geology
and data compilation is based on information reviewed or compiled by Mr Christopher Oorschot,
a Competent Person who is a Member of The Australasian Institute Geoscientists. Mr Oorschot is
the Managing Director for the Company, is a full-time employee and holds shares and options in
the Company. Mr Oorschot has sufficient experience which is relevant to the style of
mineralisation and type of deposit under consideration and to the activity which he is
undertaking to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Oorschot
consents to the inclusion in this announcement of the matters based on this information in the
form and context in which it appears.
The information in this announcement that relates to the Flushing Meadows, Mt McClure and
Gordons Dam Mineral Resource Estimates is based on information compiled and generated by
yandalresources.com.au | ASX:YRL
15
Andrew Bewsher, an employee of BM Geological Services Pty Ltd (“BMGS”). Both Andrew
Bewsher and BMGS hold shares in the company. BMGS consents to the inclusion, form and
context of the relevant information herein as derived from the original resource reports. Mr
Bewsher has sufficient experience relevant to the style of mineralisation and type of deposit under
consideration and to the activity which is being undertaken to qualify as a Competent Person as
defined in the 2012 Edition of the JORC ‘Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves’.
YRL confirms that it is not aware of any new information or data that materially affects the
information included in the original market announcement. The Company confirms that the form
and context in which the Competent Person’s findings are presented have not been materially
modified from the original market announcement.
Forward Looking Statements
This document may contain certain forward-looking statements. Forward-looking statements
include, but are not limited to, statements concerning Yandal Resources Limited’s (Yandal’s)
current expectations, estimates and projections about the industry in which Yandal operates,
and beliefs and assumptions regarding Yandal’s future performance. When used in this
document, words such as “anticipate”, “could”, “plan”, “estimate”, “expects”, “seeks”,
“intends”, “may”, “potential”, “should”, and similar expressions are forward-looking statements.
Although Yandal believes that its expectations reflected in these forward-looking statements are
reasonable, such statements are subject to known and unknown risks, uncertainties and other
factors, some of which are beyond the control of Yandal and no assurance can be given that
actual results will be consistent with these forward-looking statements. Drilling results presented
indicate geological potential for mineralisation but there can be no certainty that these results
will eventually form part of a Mineral Resource Estimate.
yandalresources.com.au | ASX:YRL
16
Tenement Schedule as at 30 June 2024
Locality
Interest
acquired
during
the
Quarter
Interest
disposed
during the
Quarter
Tenement ID
Status
Holder
Ownership
at Quarter
End
E53/1882
Granted
Yandal
100%
-
-
Notes
Ironstone Well Gold Project
Oblique/Quarter Moon
Flushing Meadows
E53/1963
Granted
Yandal
100%
-
Wiluna
ELA53/2191
Application
Legendre
100%
-
-
1
Wiluna
ELA53/2192
Application
Legendre
100%
-
-
1
Wiluna
ELA53/2193
Application
Legendre
100%
-
-
1
Wiluna
ELA53/2194
Application
Legendre
100%
-
-
1
Flushing Meadows Haul Rd
LA53/222
Application
Yandal
100%
-
-
Ironstone Well
M53/1093
Granted
Yandal
100%
-
-
Ironstone Well
ELA53/2334
Application
Yandal
100%
-
-
Flushing Meadows
MLA53/1108
Application
Yandal
100%
-
-
Lupton Well
ELA53/2295
Withdrawn
Yandal
0%
-
100%
Newcombe
E53/2304
Granted
Yandal
100%
-
-
New England
E53/1843
Granted
Yandal
100%
-
-
New England
P53/1638
Surrendered
Yandal
0%
-
100%
New England
P53/1639
Surrendered
Yandal
0%
-
100%
Mazzucco
P53/1704
Granted
Yandal
100%
-
-
Greenstone Hill
P53/1714
Granted
Yandal
100%
-
-
Greenstone Hill
P53/1715
Granted
Yandal
100%
-
-
Success
M36/691
Granted
Yandal
100%
-
-
Parmelia
M36/692
Granted
Yandal
100%
-
-
Challenger
M36/693
Granted
Yandal
100%
-
-
Mt McClure
P36/1892
Granted
Yandal
100%
-
-
Mt McClure
P36/1893
Granted
Yandal
100%
-
-
Mt McClure
P36/1894
Granted
Yandal
100%
-
-
Mt McClure
P36/1895
Granted
Yandal
100%
-
-
Mt McClure
P36/1896
Granted
Yandal
100%
-
-
Success
P36/1922
Granted
Yandal
100%
-
-
Mt McClure
P36/1934
Granted
Yandal
100%
-
-
Mt McClure
P36/1935
Granted
Yandal
100%
-
-
Mt McClure
P36/1936
Granted
Yandal
100%
-
-
Mt McClure
P36/1937
Granted
Yandal
100%
-
-
Mt McClure
P36/1938
Granted
Yandal
100%
-
-
Mt McClure
P36/1939
Granted
Yandal
100%
-
-
Mt McClure
P36/1940
Granted
Yandal
100%
-
-
Mt McClure
P36/1941
Granted
Yandal
100%
-
-
Mt McClure
P36/1942
Granted
Yandal
100%
-
-
Mt McClure
P36/1943
Granted
Yandal
100%
-
-
Mt McClure
P36/1944
Granted
Yandal
100%
-
-
Barwidgee Gold Project
Mt McClure Gold Project
yandalresources.com.au | ASX:YRL
17
Tenement Schedule as at 30 June 2024
Interest
acquired
during
the
Quarter
Interest
disposed
during the
Quarter
Tenement ID
Status
Holder
Ownership
at Quarter
End
Mt McClure
P36/1945
Granted
Yandal
100%
-
-
Mt McClure
P36/1946
Granted
Yandal
100%
-
-
Mt Jewell
E24/198
Granted
Yandal
100%
-
-
Mt Jewell
E27/536
Granted
Yandal
100%
-
-
Mt Jewell
P27/2206
Granted
Yandal
100%
-
-
Mt Jewel
MLA27/518
Application
Yandal
100%
-
-
Mulgarrie
E27/570
Granted
Yandal
100%
-
-
Gordons
E27/601
Granted
Yandal
100%
-
-
Locality
Notes
Gordons Gold Project
Wild Dog
E27/602
Granted
Yandal
100%
-
-
Gordons
LA27/100
Application
Yandal
100%
-
-
Gordons
LA27/101
Application
Yandal
100%
-
-
Gordons
M27/11
Granted
Yandal
100%
-
-
Mulgarrie
M27/237
Granted
Yandal
100%
-
-
Kanowna
M27/502
Granted
Yandal
100%
-
-
Gordons
M27/522
Application
Yandal
100%
-
-
Gordons
P26/4577
Granted
Yandal
100%
-
-
Gordons
P27/2456
Granted
Moho/Yandal
100%
-
-
Kanowna
P27/2325
Granted
Yandal
100%
-
-
Mt Eba
P27/2331
Granted
Yandal
100%
-
-
Gordons
P27/2332
Granted
Yandal
100%
-
-
Gordons
P27/2338
Granted
Yandal
100%
-
-
Gordons
P27/2339
Granted
Yandal
100%
-
-
Gordons
P27/2340
Granted
Yandal
100%
-
-
Gordons
P27/2341
Granted
Yandal
100%
-
-
Gordons
P27/2342
Granted
Yandal
100%
-
-
Gordons
P27/2343
Granted
Yandal
100%
-
-
Gordons
P27/2344
Granted
Yandal
100%
-
-
Gordons
P27/2345
Granted
Yandal
100%
-
-
Gordons
P27/2346
Granted
Yandal
100%
-
-
Gordons
P27/2354
Granted
Yandal
100%
-
-
Gordons
P27/2355
Granted
Yandal
100%
-
-
Gordons
P27/2356
Granted
Yandal
100%
-
-
Gordons
P27/2357
Granted
Yandal
100%
-
-
Gordons
P27/2358
Granted
Yandal
100%
-
-
Gordons
P27/2359
Granted
Yandal
100%
-
-
Gordons
P27/2360
Granted
Yandal
100%
-
-
Gordons
P27/2361
Granted
Yandal
100%
-
-
Gordons
P27/2362
Granted
Yandal
100%
-
-
Gordons
P27/2363
Granted
Yandal
100%
-
-
Gordons
P27/2364
Granted
Yandal
100%
-
-
Gordons
P27/2461
Granted
Yandal
100%
-
-
yandalresources.com.au | ASX:YRL
2
18
Tenement Schedule as at 30 June 2024
Locality
Interest
acquired
during
the
Quarter
Interest
disposed
during the
Quarter
Notes
3
Holder
Ownership
at Quarter
End
Application
Moho
100%
-
-
Application
Yandal
100%
100%
-
Application
Yandal
100%
-
-
Tenement ID
Status
Gordons
ELA27/701
Gordons
PLA27/2577
ELA26/229
Share your feedback
Discover