Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
ASX Announcement
30 April 2024
MARCH 2024 - QUARTERLY ACTIVITIES REPORT
KEY POINTS
Ironstone Well-Barwidgee
•
Late in the quarter an RC drilling program comprising approximately 4,500m
commenced at the Ironstone Well – Barwidgee Gold Project, located approximately
50km south of the Jundee gold operation (ASX: NST) in the northern Yandal Belt.
•
Drilling progress has been slower than anticipated due to a significant rain event in
March, however, results from the first three holes at Oblique have been received and
have confirmed that mineralisation extends at least 500m north of any previous
Yandal drilling at the prospect. Notable intercepts include:
15m @ 1.7 g/t Au from 74m (24IWBRC0002),
including 3m @ 5.3g/t Au from 79m
3m @ 1.5/t Au from 66m (24IWBRC0001),
•
Following completion of RC Drilling at Oblique, drilling will test the nearby Quarter
Moon prospect. Both prospects are located approximately 5km from the Company’s
268,000oz Flushing Meadows Mineral resource (see table on Page 10).
•
A diamond drilling program is scheduled to commence in May, testing for deeper
extensions of Oblique and Quarter Moon and to provide structural information at New
England Granite ahead of RC drill testing.
•
Other progress during the Quarter includes the completion of a drone magnetic
survey over Oblique to provide better resolution of alteration and structural controls,
the completion of a ground gravity survey over the northern half of the project and
the commencement of a comprehensive soil sampling program to test emerging
gold targets and as a first pass screen for other commodities.
Gordons
•
A soil sampling program commenced over the lesser explored areas of Gordons to
assist in geological interpretation and future drill targeting.
Corporate
•
Approx. $7.3m in cash and cash equivalents available at the end of the Quarter.
•
During the quarter, the Company completed a $2.5m “top-up” placement to enable
expanded and accelerated exploration across key prospects. Yandal Resources is
well funded to continue a high level of exploration activity through 2024.
Contact Us
A: Level 1 Unit 5/62 Ord Street,
West Perth WA 6005
T: +61 (0)8 9389 9021
E: yandal@yandalresources.com.au
yandalresources.com.au | ASX:YRL
Board and Management
Tim Kennedy
Managing Director/CEO
Greg Evans
Non-Exec Chairman
Katina Law
Non-Exec Director
Chris Oorschot
Technical Director
Greg Fitzgerald
Company Secretary
For further information or to ask questions in relation to this announcement, please visit our
Investor Hub at https://investorhub.yandalresources.com.au/link/mepOJy
Yandal Resources Ltd (ASX: YRL, “Yandal Resources” or the “Company”) is pleased to provide a
summary of operational and corporate activities undertaken during the quarter ending 31 March
2024.
The Company remains focused on exploring its portfolio of highly prospective 100% owned gold
projects located in the Yandal and Norseman-Wiluna Greenstone Belts in Western Australia
(Figure 1).
March Quarter Operational Summary and 2024 Outlook
During the March Quarter, the Company concentrated its exploration efforts on advanced
prospects within the Ironstone Well–Barwidgee Project located in the northern Yandal Belt.
Preparations were made for an extensive drilling campaign covering Quarter Moon, Oblique,
and New England Granite. Drilling operations commenced in March 2024; however, progress was
hindered by a significant rain event affecting the northern Goldfields, leading to slower-thanexpected progress. Now that ground conditions have improved, drilling progress is expected to
normalise.
Additional progress made during the Quarter at Ironstone Well includes the completion of a
drone magnetic survey over Oblique to enhance the resolution of magnetic alteration and
structural controls. Further, a gravity survey covering the northern half of the project was
completed, and a comprehensive soil sampling program commenced, which will aid in the
assessment of emerging gold targets and other commodities of interest.
A soil sampling program commenced over the lesser explored areas of Gordons to aid in
geological interpretation and future drill targeting.
In February, the Company concluded a "top-up" capital raising of $2.5m, providing the necessary
funding to expand and accelerate exploration activities in our primary target areas and to
advance new and emerging targets.
yandalresources.com.au | ASX:YRL
2
IRONSTONE
WELLBARWIDGEE
The 100% owned IWB
Gold Project covers
approximately 370km²
of contiguous, highly
prospective
and
under-explored tenure
located between the
Jundee
and
Bronzewing mines in
the northern Yandal
Greenstone
Belt
(Figure1).
Yandal
has
an
established Resource
of 268,000oz of gold at
Flushing Meadows and
considers there to be
strong potential to
make new discoveries
and
expand
this
resource base within
its’ extensive tenure
holding. Refer to the
ASX announcement of
4 November 2020 for
details of the Flushing
Meadows Resource.
The project area has
several
prospects
where limited historic
Figure 1: Ironstone Well / Barwidgee Project Overview showing the
and YRL drilling has
returned robust gold outline of YRL tenure, regional interpreted bedrock geology, and the
location of prospects discussed in this report. Dashed red line is a circle
intercepts,
indicating
with a 5km radius highlighting the proximity between the Flushing
Meadows Deposit and the Oblique and Quarter Moon Prospects.
the potential for large
scale discoveries which
are the focus of ongoing exploration. These prospects include Quarter Moon and Oblique,
which together with the nearby Flushing Meadows deposit, have the potential to develop
into a gold “camp” as well as the earlier stage New England Granite towards the southern
end of the project.
yandalresources.com.au | ASX:YRL
3
Drilling
In March 2024, an RC drilling program of approximately 4,500m commenced at the Oblique
and Quarter Moon Prospects.
RC drilling at Oblique will follow up a number of significant intercepts from the phase 2 RC
drilling completed in the previous quarter (See ASX release 12th January 2024), including;
24m @ 1.8 g/t Au from 60m (YRLRC1177),
3m @ 11.4 g/t Au from 102m (YRLRC1175),
9m @ 1.9 g/t Au from 63m (YRLRC1171),
including 2m @ 16.9 g/t Au from 102m
including 2m @ 6.5 g/t Au from 66m
13m @ 1.1 g/t Au from 93m (YRLRC1169)
In addition, RC drilling will also test regolith anomalies across the northern half of the prospect
(see Figure 2).
Subsequent to quarters end, the Company received results from the first three holes in the
current program. The results confirm the presence of broad and high-grade mineralisation
500m north of any previous RC drilling completed by Yandal Resources. Notable intercepts
include (Figure 2 and Figure 3):
•
15m @ 1.7 g/t Au from 74m (24IWBRC0002),
•
including 3m @ 5.3g/t Au from 79m
3m @ 1.5/t Au from 66m (24IWBRC0001),
Full details of the initial RC results are available in Yandal’s ASX release of 29th April 2024.
A diamond drilling program at Oblique, Quarter Moon and New England Granite prospect
will follow in May. Diamond drilling at Oblique and Quarter Moon will include several broadspaced holes as a framework program to test the depth extensions of mineralisation within
fresh rock and the broader scale and strike extents of the mineralised systems.
Two 400m deep diamond holes are planned across the New England Granite Prospect and
are co-funded under the Geological Survey of Western Australia Exploration Incentive
Scheme. The two holes will test the sheared southern margin of the granitoid adjacent to the
Barwidgee Shear Zone and the anomalous eastern margin. The resultant data will assist in
the design of a broader RC program across the prospect scheduled for the June Quarter.
yandalresources.com.au | ASX:YRL
4
YRL Drilling 500m
north of 2023
program
Surface Projection
of OBL01 Structure
Interpreted surface
projection of the high
magnetic unit
Figure 2: A Collar plan for the Oblique Prospect displaying all drilling collars, colour-coded by
max Au in hole (g/t Au), overlying a composite aerial magnetic image e (RTP 1VD non-linear
and RTP 2VD non-linear). Interpreted surface projections of the magnetite-chlorite altered
unit and the projection of the OBL01 structure to the surface (based on drilling intercepts) are
also plotted and labelled.
yandalresources.com.au | ASX:YRL
5
SW
NE
Surface
3m @ 1.5 g/t Au
15m @ 1.7 g/t Au
Incl. 3m @ 5.3 g/t Au
TOFR
Figure 3: Oblique cross-section A (see Figure 2 plan for section location), showing RC drilling
results from 24IWBRC0001 and 24IWBRC0002, with a preliminary interpretation of
mineralisation (red polygons).
yandalresources.com.au | ASX:YRL
6
Soil Sampling
Following
a
successful
orientation soil program across
selected areas of the Ironstone
Well–Barwidgee Gold Project
(IWB) last quarter, a large-scale
follow-up soil program has
commenced. The program will
comprise approximately 1800
samples on 400m x 200m
spaced grid across much of the
northern part of the project
(refer to ASX Announcement 26
February 2024). This work will
result in a consistent and
comprehensive geochemical
dataset across a significant
portion of IWB and will assist in
ongoing targeting for gold,
lithium and other commodities.
Approximately 60% of the
planned samples have been
collected with the program
expected to be complete by
mid May 2024 (Refer to Figure
4).
Drone Magnetics
A drone aerial magnetic survey
was completed over the
Oblique Prospect to improve the Figure 4: Ironstone Well-Barwidgee Project Overview showing
the location of soil, drone magnetics and gravity surveys
resolution of aerial magnetic
commenced during the March 24 Quarter.
data from a line spacing of 100m
down to a 25m line spacing. Process data has been received, and interpretations are
underway (Refer to Figure 4).
Gravity
A broad-scale ground gravity survey was recently completed across the northeastern half
of the IWB Project and a smaller area around the New England Granite Prospect (see Figure
4). The survey utilised 200m by 200m spaced gravity stations across a portion of the
yandalresources.com.au | ASX:YRL
7
northeastern IWB project area, which has poor aerial magnetic resolution due to deeper
weathering and transported cover/paleochannels. The data set will significantly boost the
Company’s ability to interpret major stratigraphic packages and regional structures in a
poorly understood portion of the project. Data from the ground gravity survey is currently
being processed.
GORDONS
A soil sampling program was commenced across the eastern half of the Gordons Gold
Project. The program aims to build a comprehensive surface geochemical dataset that can
be interrogated to aid in exploration targeting, focusing on emerging targets in the south of
the Project. The program will collect 100m spaced samples on 400m spaced lines across
selected areas of the Project. Initial results from the soil sampling program are due before
the end of July.
LOOKING AHEAD
The Company is well funded after a top-up capital raise of $2.5 million in February 2024 and
has a very active H1 CY 2024 planned with priority exploration activities, including;
1.
Completion of the current RC program. Follow-up diamond drilling is scheduled for May
across Oblique and Quarter Moon;
2.
The refinement of exploration targets for follow-up RC drilling across the 4.2km eastern
granite margin of the New England Granite (NEG) Prospect is underway. This will be
assisted through Exploration Incentive Scheme co-funding to support the completion
of two deep (400m) diamond holes across the NEG prospect. Drilling is scheduled for
late May and June.
3.
The soil sampling program will be completed before the end of April; initial laboratory
results are expected in June.
4.
The recently acquired ground gravity data is scheduled for processing in early May.
Once processed, this will be incorporated into a review of emerging and conceptual
exploration targets across the Ironstone Well-Barwidgee Project will commence.
CORPORATE SUMMARY
Capital Raising
During the quarter, the Company completed a placement raising $2.5m (before costs). The
placement was oversubscribed and strongly supported by major shareholders and had
significant interest from new investors. This was a “top up” of the November 2023 capital
raising in response to positive drilling results announced in January. The 31.2m placement
shares were priced at $0.08. In addition, 1.9m shares were issued to MST Financial Services
yandalresources.com.au | ASX:YRL
8
Pty Ltd at an issue price of $0.08 per share as payment of fees owing for services rendered
as the sole lead manager to the placement.
Funds raised will be used to expand and further accelerate exploration, including:
• RC and diamond drill testing and Mineral Resource Estimation related activities at
Exploration Targets within the Ironstone Well-Barwidgee Project and;
• advancement of high priority targets at the Mt McClure and Gordons projects.
Issued Capital
Other than the securities issued pursuant to the capital raising outlined above, the only other
movements in securities on issue during the quarter were the issue of 700,000 options under
the Company’s Employee Incentive Scheme with full details provided in Appendix 3G on 1
March 2024.
As at 31 March 2024, the Company had the following securities on issue:
Type of Security
31 March 2024
31 December 2023
Ordinary shares
267,807,614
234,726,156
Options
76,466,071
75,766,071
375,000
375,000
344,648,685
310,867,227
Performance rights
TOTAL
Summary of Exploration Expenditure
In accordance with Listing Rule 5.3.1, Yandal confirms that as disclosed in the Cashflow
Report (item 1.2(a)), Yandal’s exploration expenditure for the quarter was approximately
$736k, details of the exploration activities underlying this expenditure are as set out in the
Activities Report.
Payments to Related Parties and their Associates
In accordance with ASX Listing Rule 5.3.5, $171k was paid to related parties or their associates
during the quarter, comprising Executive Director salaries, Non-executive Director fees and
superannuation.
Authorised by the board of Yandal Resources
For further information, please contact:
Tim Kennedy
Managing Director
Yandal Resources Limited
yandal@yandalresources.com.au
yandalresources.com.au | ASX:YRL
Greg Fitzgerald
Company Secretary
+61 8 9389 9021
yandal@yandalresources.com.au
9
About Yandal Resources Limited
Yandal Resources was listed on the ASX in December 2018 and has a portfolio of advanced gold
exploration projects in the highly prospective Yandal and Norseman-Wiluna Greenstone Belts of Western
Australia.
Figure 5: Yandal Resources’ gold project locations.
Yandal Resources Ltd - Mineral Resource Summary
Indicated
Inferred
Deposit
Tonnes Grade
Au
Tonnes
Grade
Au
(‘000s)
(g/t)
(oz)
(‘000)
(g/t)
(oz)
Ironstone Well
Flushing Meadows1
2,141
1.3
91,000
5,245
1.1
177,000
Mt McClure
Challenger2
718
1.9
44,000
Success3
1,255
1.9
75,000
4
Parmelia
252
2.1
17,000
5
HMS Sulphur
1010
1.2
39,000
Gilmore6
134
1.7
7,200
Sub-total - MMC
3,369
1.7
182,200
Gordons
Gordons Dam7
365
1.7
20,000
8
2,141
Grand-total
8,979
1.3
379,200
1.3
91,000
Total
Tonnes
(000’s)
Grade
(g/t)
Au
(Oz)
7,386
1.1
268,000
718
1.9
44,000
1,255
1.9
75,000
252
2.1
17,000
1010
1.2
39,000
134
3,369
1.7
1.7
7,200
182,200
365
1.7
20,000
11,120
1.4
470,200
Due to the effects of rounding, totals may not represent the sum of the individual
components.
1. Reported above 0.5g/t Au lower cut-off grade; refer to Yandal Resources Ltd ASX announcement dated 4 November
2020 for full details. 2. Reported above 1.0g/t Au lower cut-off grade; refer to Yandal Resources Ltd ASX announcement
dated 22 August 2022 for full details 3. Reported above 1.0g/t Au lower cut-off grade; refer to Yandal Resources Ltd ASX
announcement dated 6 September 2022 for full details.4. Reported above 1.0g/t Au lower cut-off grade; refer to Yandal
Resources Ltd ASX announcement dated 20 September 2022 for full details 5. Reported above 0.5g/t Au lower cut-off
grade within this announcement 6. Reported above 1.0g/t Au lower cut-off grade within this announcement 7. Reported
above 1.0g/t Au lower cut-off grade; refer to Yandal Resources Ltd ASX announcement dated 6 April 2023 for full details
8. All Resources are reported as global estimates, not constrained by optimised pit shells.
yandalresources.com.au | ASX:YRL
10
Competent Person Statement
The information in this document related to Exploration Targets and Exploration Results, geology
and data compilation is based on information reviewed or compiled by Mr Christopher Oorschot,
a Competent Person who is a Member of The Australasian Institute Geoscientists. Mr Oorschot is
the Exploration Manager and Technical Director for the Company, is a full-time employee and
holds shares and options in the Company. Mr Oorschot has sufficient experience which is relevant
to the style of mineralisation and type of deposit under consideration and to the activity which
he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the
‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr
Oorschot consents to the inclusion in this announcement of the matters based on this information
in the form and context in which it appears.
The information in this announcement that relates to the Flushing Meadows, Mt McClure and
Gordons Dam Mineral Resource Estimates is based on information compiled and generated by
Andrew Bewsher, an employee of BM Geological Services Pty Ltd (“BMGS”). Both Andrew
Bewsher and BMGS hold shares in the company. BMGS consents to the inclusion, form and
context of the relevant information herein as derived from the original resource reports. Mr
Bewsher has sufficient experience relevant to the style of mineralisation and type of deposit under
consideration and to the activity which is being undertaken to qualify as a Competent Person as
defined in the 2012 Edition of the JORC ‘Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves’.
YRL confirms that it is not aware of any new information or data that materially affects the
information included in the original market announcement. The company confirms that the form
and context in which the Competent Person’s findings are presented have not been materially
modified from the original market announcement.
Forward Looking Statements
This document may contain certain forward-looking statements. Forward-looking statements
include, but are not limited to, statements concerning Yandal Resources Limited’s (Yandal’s)
current expectations, estimates and projections about the industry in which Yandal operates,
and beliefs and assumptions regarding Yandal’s future performance. When used in this
document, words such as “anticipate”, “could”, “plan”, “estimate”, “expects”, “seeks”,
“intends”, “may”, “potential”, “should”, and similar expressions are forward-looking statements.
Although Yandal believes that its expectations reflected in these forward-looking statements are
reasonable, such statements are subject to known and unknown risks, uncertainties and other
factors, some of which are beyond the control of Yandal and no assurance can be given that
actual results will be consistent with these forward-looking statements. Drilling results presented
indicate geological potential for mineralisation but there can be no certainty that these results
will eventually form part of a Mineral Resource Estimate.
yandalresources.com.au | ASX:YRL
11
Tenement Schedule as at 31 March 2024
Interest
acquired
during
the
Quarter
Interest
disposed
during the
Quarter
Tenement ID
Status
Holder
Ownership
at Quarter
End
Oblique/Quarter Moon
E53/1882
Granted
Yandal
100%
-
-
Flushing Meadows
E53/1963
Granted
Yandal
100%
-
-
Wiluna
ELA53/2191
Application
Legendre
100%
-
-
1
Wiluna
ELA53/2192
Application
Legendre
100%
-
-
1
Wiluna
ELA53/2193
Application
Legendre
100%
-
-
1
Wiluna
ELA53/2194
Application
Legendre
100%
-
-
1
Flushing Meadows Haul Rd
LA53/222
Application
Yandal
100%
-
-
Locality
Notes
Ironstone Well Gold Project
Ironstone Well
M53/1093
Granted
Yandal
100%
-
Ironstone Well
ELA53/2334
Application
Yandal
100%
100%
-
Flushing Meadows
MLA53/1108
Application
Yandal
100%
-
-
Lupton Well
ELA53/2295
Application
Yandal
100%
Newcombe
ELA53/2304
Application
Yandal
100%
-
-
New England
E53/1843
Granted
Yandal
100%
-
-
New England
P53/1638
Granted
Yandal
100%
-
-
New England
P53/1639
Granted
Yandal
100%
-
-
Mazzucco
P53/1704
Granted
Yandal
100%
-
-
Greenstone Hill
P53/1714
Granted
Yandal
100%
-
-
Greenstone Hill
P53/1715
Granted
Yandal
100%
-
-
Success
M36/691
Granted
Yandal
100%
-
-
Parmelia
M36/692
Granted
Yandal
100%
-
-
Challenger
M36/693
Granted
Yandal
100%
-
-
Mt McClure
P36/1892
Granted
Yandal
100%
-
-
Mt McClure
P36/1893
Granted
Yandal
100%
-
-
Mt McClure
P36/1894
Granted
Yandal
100%
-
-
Mt McClure
P36/1895
Granted
Yandal
100%
-
-
Mt McClure
P36/1896
Granted
Yandal
100%
-
-
Success
P36/1922
Granted
Yandal
100%
-
-
Mt McClure
P36/1934
Granted
Yandal
100%
-
-
Mt McClure
P36/1935
Granted
Yandal
100%
-
-
Mt McClure
P36/1936
Granted
Yandal
100%
-
-
Mt McClure
P36/1937
Granted
Yandal
100%
-
-
Mt McClure
P36/1938
Granted
Yandal
100%
-
-
Mt McClure
P36/1939
Granted
Yandal
100%
-
-
Mt McClure
P36/1940
Granted
Yandal
100%
-
-
Mt McClure
P36/1941
Granted
Yandal
100%
-
-
Mt McClure
P36/1942
Granted
Yandal
100%
-
-
Mt McClure
P36/1943
Granted
Yandal
100%
-
-
Barwidgee Gold Project
Mt McClure Gold Project
yandalresources.com.au | ASX:YRL
12
Tenement Schedule as at 31 March 2024
Interest
acquired
during
the
Quarter
Interest
disposed
during the
Quarter
Tenement ID
Status
Holder
Ownership
at Quarter
End
Mt McClure
P36/1944
Granted
Yandal
100%
-
-
Mt McClure
P36/1945
Granted
Yandal
100%
-
-
Mt McClure
P36/1946
Granted
Yandal
100%
-
-
E24/198
Granted
Yandal
100%
-
-
Mt Jewell
E27/536
Granted
Yandal
100%
-
-
Mt Jewell
P27/2206
Granted
Yandal
100%
-
-
Mt Jewel
MLA27/518
Application
Yandal
100%
-
-
Mulgarrie
E27/570
Granted
Yandal
100%
-
-
Gordons
E27/601
Granted
Yandal
100%
-
-
Wild Dog
E27/602
Granted
Yandal
100%
-
-
Locality
Notes
Gordons Gold Project
Mt Jewell
Mt Vetters
E27/605
Granted
Yandal
0%
-
100%
Gordons
LA27/100
Application
Yandal
100%
-
-
Gordons
LA27/101
Application
Yandal
100%
-
-
Gordons
M27/11
Granted
Yandal
100%
-
-
Mulgarrie
M27/237
Granted
Yandal
100%
-
-
Kanowna
M27/502
Granted
Yandal
100%
-
-
Gordons
M27/522
Application
Yandal
100%
100%
-
Gordons
P26/4577
Granted
Yandal
100%
-
-
Gordons
P27/2456
Granted
Moho/Yandal
100%
-
-
Mulgarrie
P27/2234
Granted
Yandal
100%
-
-
Kanowna
P27/2325
Granted
Yandal
100%
-
-
Mt Eba
P27/2331
Granted
Yandal
100%
-
-
Gordons
P27/2332
Granted
Yandal
100%
-
-
Gordons
P27/2338
Granted
Yandal
100%
-
-
Gordons
P27/2339
Granted
Yandal
100%
-
-
Gordons
P27/2340
Granted
Yandal
100%
-
-
Gordons
P27/2341
Granted
Yandal
100%
-
-
Gordons
P27/2342
Granted
Yandal
100%
-
-
Gordons
P27/2343
Granted
Yandal
100%
-
-
Gordons
P27/2344
Granted
Yandal
100%
-
-
Gordons
P27/2345
Granted
Yandal
100%
-
-
Gordons
P27/2346
Granted
Yandal
100%
-
-
Gordons
P27/2354
Granted
Yandal
100%
-
-
Gordons
P27/2355
Granted
Yandal
100%
-
-
Gordons
P27/2356
Granted
Yandal
100%
-
-
Gordons
P27/2357
Granted
Yandal
100%
-
-
Gordons
P27/2358
Granted
Yandal
100%
-
-
Gordons
P27/2359
Granted
Yandal
100%
-
-
Gordons
P27/2360
Granted
Yandal
100%
-
-
Gordons
P27/2361
Granted
Yandal
100%
-
-
Gordons
P27/2362
Granted
Yandal
100%
-
-
yandalresources.com.au | ASX:YRL
2
13
Tenement Schedule as at 31 March 2024
Interest
acquired
during
the
Quarter
Interest
disposed
during the
Quarter
Tenement ID
Status
Holder
Ownership
at Quarter
End
Gordons
P27/2363
Granted
Yandal
100%
-
-
Gordons
P27/2364
Granted
Yandal
100%
-
-
Locality
Gordons
P27/2461
Granted
Yandal
100%
-
-
Gordons
ELA27/701
Application
Moho
100%
100%
-
ELA26/229
Application
Yandal
100%
-
-
Notes
3
White Dam
White Dam
Notes:
1.
2.
3.
In July 2022, a Purchase agreement was executed with Bruce Legendre to acquire these tenements when they
are granted.
In November 2021, a Heads of Agreement was executed with Moho Resources Limited that provides for Yandal
Resources to acquire a 100% interest in the gold and related metals rights over granted Tenements.
In June 2023, a purchase agreement was entered into with Moho Resources for Yandal Resources to acquire 100%
interest in the tenement upon grant, with Moho retaining a gold royalty and certain non-gold rights.
yandalresources.com.au | ASX:YRL
14
Appendix 1 – Ironstone Well-Barwidgee Gold Project
JORC Code (2012) Table 1, Sections 1 and 2
Mr Christopher Oorschot, Exploration Manager and Technical Director of Yandal Resources, compiled the information in Section 1 and Section 2 of the
following JORC Table 1 and is the Competent Person for those sections. The following Table and Sections are provided to ensure compliance with the
JORC Code (2012 edition) requirements for the reporting of Exploration Results.
Section 1 Sampling Techniques and Data
Criteria
JORC Code explanation
Commentary
Sampling
techniques
Nature and quality of sampling (e.g. cut channels, random
chips, or specific specialised industry standard
measurement tools appropriate to the minerals under
investigation, such as down hole gamma sondes, or
handheld XRF instruments, etc.). These examples should
not be taken as limiting the broad meaning of sampling.
•
•
•
Include reference to measures taken to ensure sample
representivity and the appropriate calibration of any
measurement tools or systems used.
•
•
Aspects of the determination of mineralisation that are
Material to the Public Report. In cases where ‘industry
standard’ work has been done this would be relatively
simple (e.g. ‘reverse circulation drilling was used to obtain
1 m samples from which 3 kg was pulverised to produce a
30 g charge for fire assay’). In other cases more
yandalresources.com.au | ASX:YRL
•
Yandal Resources (YRL) RC Samples were collected via a rig-mounted static cone splitter,
splitting approximately 12.5% of the total sample volume. Two splits are collected for each
metre: a primary sample and a duplicate sample. The primary 1m samples are then sent to a
lab for further analysis. The duplicate samples are retained on-site unless they are submitted as
routine duplicates.
For historical RC drilling, sampling practices by previous operators are assumed to be industry
standard at that time. Sampling procedures would be comparable to those applied by Yandal
Resources as per the above but with variations in the type of splitter used, etc.
Historic core sampling procedures are unknown and are assumed to be industry standard at
that time. Historic core samples have not been retained by the project and are unavailable
for review.
For YRL RC drilling, the cone splitter is regularly cleaned and inspected. The 1m bulk samples
are laid out in drill order. These bulk samples are regularly inspected for contamination, and
the volume of the bulk sample is monitored. These bulk samples are retained until all results are
received and may be used to collect additional field duplicates to verify lab results, logged
geology or any other form of analysis. If the bulk sample appears visually low in volume or
weight, this is recorded with the sample details. The same applies to damp or wet samples.
Two splits are collected for each metre drilled: a primary sample and a secondary sample. The
Secondary sample is retained on-site and may be used to collect additional field duplicates
to verify lab results, logged geology or any other form of analysis
For all results, RC drilling was used to obtain 1m samples from which a portion, between 1-3kg
in weight, was crushed and pulverised to produce a 50g charge for fire assay with an AAS
(atomic absorption spectroscopy) finish for gold determination with a 0.01ppm detection limit.
15
Criteria
JORC Code explanation
Commentary
explanation may be required, such as where there is
coarse gold that has inherent sampling problems. Unusual
commodities or mineralisation types (e.g. submarine
nodules) may warrant disclosure of detailed information.
Drilling
techniques
Drill type (e.g. core, reverse circulation, open-hole
hammer, rotary air blast, auger, Bangka, sonic, etc) and
details (e.g. core diameter, triple or standard tube, depth
of diamond tails, face-sampling bit or other type, whether
core is oriented and if so, by what method, etc).
•
•
For YRL RC drilling, a 139mm diameter face sampling bit and hammer was used.
For historical RC drilling, a 5’ ¼ inch face sampling bit and hammer was used.
Drill sample
recovery
Method of recording and assessing core and chip sample
recoveries and results assessed.
•
For YRL holes, RC drilling recoveries are visually assessed by the supervising geologist, and any
low-volume or weight samples are recorded, along with any damp or wet samples. Drill depths
are routinely verified at the completion of each drill rod (every 6m). The cone splitter is checked
for each drill site to ensure it is completely upright and level. Sample collection from the splitter
by drilling off-siders is monitored for any inefficiencies. For deeper holes, larger drilling
equipment is used, with boos
Share your feedback