Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
ASX Announcement
22 January 2024
DECEMBER 2023 - QUARTERLY ACTIVITIES REPORT
KEY POINTS
Ironstone Well-Barwidgee
•
Phase 2 RC drilling at the large-scale Oblique prospect confirmed the presence of multiple mineralised
structures cross-cutting the magnetic stratigraphy, returning a number of strong intercepts, including:
o 24m @ 1.8 g/t Au from 60m (YRLRC1177),
o 3m @ 11. 4g/t Au from 102m (YRLRC1175),
including 2m @ 16.9g/t Au from 102m
o 9m @ 1.9 g/t Au from 63m (YRLRC1171),
including 2m @ 6.5g/t Au from 66m
o 13m @ 1.1g/t Au from 93m (YRLRC1169)
•
Geological interpretation indicates a large structure, designated OBL01, as a major prospect scale control
on mineralisation. Significantly, this structure is essentially un-tested to the northwest and southeast,
with potential parallel structures opening up additional priority drilling targets within and peripheral to the
main Oblique mineralisation trend.
•
The next phase of drilling is scheduled to commence in late March 2024 and will include RC and diamond
follow-up of key positions at Oblique as well as other high-priority prospects including RC drilling at Quarter
Moon and EIS Co-funded diamond drilling at New England Granite.
•
An initial review of the lithium prospectivity across the Ironstone Well-Barwidgee Project has identified
several broad areas of interest. An orientation soil sampling program has been completed (results pending).
•
Successful application for EIS Co-funding support of diamond drilling at the New England Granite prospect.
Corporate
•
•
•
$5.7m in cash and cash equivalents available at the end of the Quarter.
During the quarter, the Company completed a placement raising $4m (before costs). The placement was
oversubscribed and strongly supported by major shareholders with significant interest from new investors.
Yandal Resources is well funded to continue a high level of exploration activity through 2024.
For further information or to ask questions in relation to this announcement, please visit our Investor Hub at
https://investorhub.yandalresources.com.au/link/8r6wGP
Registered Address
Board Members
Yandal Resources Limited
Tim Kennedy
Managing Director/CEO
Greg Evans
Chair
Katina Law
Non-Executive Director
Chris Oorschot
Technical Director
Greg Fitzgerald
Company Secretary
T
+61 8 9389 9021
E
yandal@yandalresources.com.au
W
www.yandalresources.com.au
ACN 108 753 608
A
P
ABN 86 108 753 608
Level 1, Unit 5/62 Ord Street
West Perth WA 6005
PO Box 1104
Nedlands WA 6909
Yandal Resources Ltd (ASX: YRL, “Yandal Resources” or the “Company”) is pleased to provide a
summary of operational and corporate activities undertaken during the quarter ending 31 December 2023.
The Company is focused on exploring its portfolio of highly prospective 100% owned gold projects located
in the Yandal and Norseman-Wiluna Greenstone Belts in Western Australia (Figure 1).
December Quarter Operational Summary and 2024 Outlook
During the December Quarter, the Company focused exploration on advanced prospects within the
Ironstone Well–Barwidgee Project in the northern Yandal Belt.
A Phase 2 RC drilling program was completed at the large-scale Oblique prospect, returning a number of
very strong drill intercepts and advancing the geological understanding of mineralisation, which will assist
in follow-up drill targeting. Target generation was undertaken at the Mt McClure and Gordons Projects in
preparation for planned drilling in 2024.
Following the strongly supported capital raise in November, the Company is gearing up for a very active
2024. Subject to possible weather restrictions, we anticipate commencing drilling in March at Ironstone
Well-Barwidgee. This will include diamond and RC drilling at Oblique, following up on the success of the
Phase 2 RC program, as well as first pass RC drilling at Quarter Moon. We will also be drilling two diamond
holes at New England Granite, jointly funded by the WA Government’s Exploration Incentive Scheme. We
will be assessing the results of the orientation soil geochemical program testing for lithium and other
commodities and, if warranted will be planning a much larger soil sampling program at IWB. An initial
assessment of the lithium potential at Mt McClure will continue and will include bottom-of-hole pXRF
analysis. At Gordons, we will be acquiring and reprocessing additional gravity data (initially public domain)
to assist in finalising drill targets over the highly prospective Gordon Sirdar Shear Zone. Drill testing of
these targets will commence upon grant of E27/701 and receipt of access approvals.
Figure 1 – Yandal Resources’ project locations.
ASX Announcement 22 January 2024
Page 2
IRONSTONE WELLBARWIDGEE
The 100% owned IWB
Gold Project covers
approximately 370km² of
contiguous,
highly
prospective and underexplored tenure located
between the Jundee and
Bronzewing mines in the
northern
Yandal
Greenstone
Belt
(Figures 2 and 3).
Yandal
has
an
established Resource of
268,000oz of gold at
Flushing Meadows and
considers there to be
strong potential to make
new discoveries and
expand this resource
base within its’ extensive
tenure holding. Refer to
the ASX announcement
of 4 November 2020 for
details of the Flushing
Meadows Resource.
The project area has
several prospects where
limited historic and YRL
drilling has returned
robust gold intercepts,
Figure 2: Location map of Ironstone Well/Barwidgee (IWB) and Mt McClure
indicating the potential for (MMC) Gold Projects showing key prospects and occurrences in relation to
nearby mines and regional geology
large scale discoveries
which are the focus of ongoing exploration. These prospects include Quarter Moon and Oblique,
which together with the nearby Flushing Meadows deposit, have the potential to develop into a gold
“camp” as well as the earlier stage New England Granite towards the southern end of the project.
The key activities during the Quarter were the completion of Phase 2 RC drilling at Oblique and the
collection of reconnaissance soil samples on the western margin of the project as an initial test of the
potential for lithium and other commodities. Full results of the RC drilling were announced to the ASX
on 12 January 2024 and are summarised below. Results from the soil sampling are still pending.
ASX Announcement 22 January 2024
Page 3
Figure 3: Ironstone Well / Barwidgee Project Overview showing the outline of YRL tenure, regional
interpreted bedrock geology, and the location of prospects discussed in this report. Dashed red line
is a circle with a 5km radius highlighting the proximity between the Flushing Meadows Deposit and
the Oblique and Quarter Moon Prospects.
ASX Announcement 22 January 2024
Page 4
Oblique
RC Drilling
Oblique is located approximately 6km northwest along strike from the Flushing Meadows Resource
and 45km south of Northern Star’s (ASX: NST) Jundee Mine (see Figure 2). Oblique and Flushing
Meadows are adjacent to the Barwidgee Shear Zone, a major regional mineralised structure. Previous
drilling highlighted that Oblique has strongly anomalous gold over a 1.9km long zone and returned
numerous intercepts, some of which are broad and contain higher-grade cores.
A review of previous drilling indicated that mineralisation occurs in multiple sub-parallel
positions with many holes ending in mineralisation or not having effectively tested the full
width of the host stratigraphic sequence. The scale of the regolith and surface anomaly, combined
with the limited effectiveness of previous drilling, prompted the prioritisation of Oblique for drilling in
2023.
The Oblique Phase 2 RC program comprised 14 holes for 2,406m along 1,100m of strike. In
addition to these holes, three previously drilled RC holes were extended for a total of 168m.
Despite difficult drilling conditions, all holes were completed to the designed depth. The program
successfully achieved its purpose, namely to:
•
Further test mineralisation within the currently defined Exploration Target extents,
•
Test for mineralisation 400m south of previous RC drilling and
•
Obtain several intercepts of mineralisation within fresh rock.
Significant intercepts are summarised below,
24m @ 1.8 g/t Au from 60m (YRLRC1177),
3m @ 11.4 g/t Au from 102m (YRLRC1175),
9m @ 1.9 g/t Au from 63m (YRLRC1171),
including 2m @ 16.9 g/t Au from 102m
including 2m @ 6.5 g/t Au from 66m
13m @ 1.1 g/t Au from 93m (YRLRC1169)
The RC drilling has refined the Company’s interpretation of the local stratigraphy and identified the
primary source of the elongate magnetic anomaly (see Figure 4) across the prospect which
correlates with a 12-16m wide magnetite-chlorite (altered) unit variably intruded by a number of
intermediate porphyry bodies. The protolith for this unit is unknown. A massive sulphide (pyrite
dominant) unit, prevalent in historical drilling in the north of the prospect, is likely the same unit but
altered by reduced fluids.
The regolith across the prospect is interpreted to be a partially eroded in-situ regime with a thin veneer
of transported colluvium in places. Weathering is deep across the prospect, with fresh rock only
evident at vertical depths between 60m and 100m.
Geological logging suggests higher-grade mineralisation is associated with quartz veining and
sulphide alteration in combination with shearing and/or brecciation.
ASX Announcement 22 January 2024
Page 5
Figure 4: Plan of the Oblique prospect showing all collars colour-coded by max Au in hole (g/t Au)
and all new drilling (not colour-coded). Overlying a composite aerial magnetic image of reduced to
pole (1VD, non-linear) and reduced to pole (2VD, non-linear). Interpreted surface projections of
the magnetite-chlorite altered unit and the OBL01 structure are also plotted and labelled.
At the prospect scale, mineralisation appears to be broadly controlled by northwest striking (striking
300° to 310°) and northeast dipping structures slightly oblique to stratigraphy (striking 320° to 330°).
The intersection of this structural trend with stratigraphy would produce a moderate (45°) plunge
towards the north, which is likely reflected in mineralisation, though further drilling is required to verify
this.
Section B in Figure 5 demonstrates the need to effectively drill through the target sequence across
the Oblique Prospect, with a majority of previous drilling ending in mineralisation due to difficult drilling
conditions. YRLRC1177 provides a significant intercept of:
24m @ 1.8g/t Au from 60m
ASX Announcement 22 January 2024
Page 6
This result is directly along the strike of several partial intercepts (drilling ended in mineralisation),
including:
13m @ 1.7g/t Au from 86m (CYPFRC15) – Historic
12m @ 1.1 g/t Au from 84m (YRLRC1157) – ASX 25th October 2023
21m @ 0.96 g/t Au from 51m (YRLRC481)
Including 4m @ 1.9 g/t Au from 68m to EOH – ASX 9th March 2021
Figure 5: Oblique cross-section A (see longitudinal section for section location), showing RC drilling
completed by the Company in November 2023 and assay results, with a preliminary interpretation of
mineralisation (red polygons).
ASX Announcement 22 January 2024
Page 7
Current interpretations suggest the broad intercept in YRLRC1177 correlates with the interaction of
an oblique northwest striking, northeast dipping mineralised structure with the magnetite-chlorite unit.
This structure has been designated OBL01 (Figure 2). Previous drilling combined with the most
recent results suggests this structure is mineralised over 300m of strike extent and open to the north.
This represents a key insight from the 2023 RC drilling program that will drive the next round of
exploration drilling across the Oblique Prospect. Significantly, the OBL01 structure, when projected
along strike to the northwest and southeast, is critically un-tested, presenting new structural targets
for future exploration beyond the Oblique Prospect.
YRLRC1175 (Figure 6 –Section A), the deepest hole completed across the Oblique prospect with
an intercept of 31m @ 0.4 g/t Au from 163m, confirming the presence of mineralisation at depth within
fresh rock (noting that samples collected were wet with some volume loss). The same drill hole also
returned a high-grade intercept in the hanging wall of:
3m @ 11.4 g/t Au from 102m (YRLRC1175),
including 2m @ 16.9 g/t Au from 102m
This result represents a parallel structure within the hanging wall of the main mineralised trend.
Drilling to the south confirms the broader potential for additional mineralised structures to the south.
These intercepts include
9m @ 1.9g/t Au from 63m (YRLRC1171), and
9m @ 1.0 g/t Au from 75m (YRLRC1168), and
13m @ 1.1g/t Au from 93m (YRLRC1169)
These results suggest that additional oblique structures comparable to OBL01 may be present to the
south and provide clear targets for follow-up drilling. In addition to this, historical drilling to the north
presents a number of trends comparable to OBL01 (see Figure 4).
Next Steps
Results from the drilling program confirm the potential of Oblique. Further exploration will be aimed
at identifying new and extending known mineralised structures, with a particular focus on where these
structures interact with magnetite-rich stratigraphy.
An initial diamond drilling program is scheduled for March-April 2024 to obtain further intercepts at
depth and provide detailed information regarding the host stratigraphy, structures, intrusive types and
the nature of the magnetite-rich unit across the Oblique Prospect.
In addition to this, the Company will assess options for capturing more detailed aerial magnetics
across the prospect to aid in geological interpretations and exploration targeting.
Subject to further analysis of the results and logged geology, follow-up RC drilling will be designed to
test the OBL01 structure and equivalent parallel structures along strike with a focus on completing
additional drilling in the northern half of the Prospect and further delineating newly identified structures
in the south. The aim of this work will be the projection of any newly identified structures into the
magnetite-chlorite unit to delineate high-priority targets for future drilling.
A broader projection of the interpreted OBL01 structure to the northwest and southeast also presents
new exploration targets outside of the Oblique Prospect. Subject to further verification of the OBL01
ASX Announcement 22 January 2024
Page 8
structure in the next drilling program, the projected extensions will also be evaluated as exploration
targets going forward (see Figure 4).
Figure 6: Oblique cross-section A (see longitudinal section for section location), showing RC drilling
completed by the Company in November 2023 and assay results, with a preliminary interpretation of
mineralisation (red polygons).
Lithium Review
An initial review of the pegmatite-hosted lithium prospectivity across the Ironstone Well-Barwidgee
Project has been completed. The review identified several broad areas of interest, with a regional
program designed to assess these areas commencing with the completion of a small orientation soil
sampling program in mid-November and the delineation of several areas for field reconnaissance in
early 2024. The results of the orientation soil sampling program are expected in early 2024.
ASX Announcement 22 January 2024
Page 9
Mt McClure
The Mt McClure Project is located 15km south-west of the historic Bronzewing gold mine and 10km
from the operating Orelia gold mine, both owned by Northern Star Resources Ltd (ASX: NST) in
Yandal Belt (see Figure 7). The project covers a total strike length of 17km of prospective
stratigraphy and includes several shallow historical open cut pits.
Figure 7: Mt McClure tenement plan showing the location of the HMS Sulphur and
Gilmore deposits, major prospects, interpreted bedrock lithology, major structures and
proximity to nearby mines.
ASX Announcement 22 January 2024
Page 10
The Mt McClure Mineral Resource Inventory is 182,200oz @ 1.7 g/t Au all located on granted
mining leases. Refer to the YRL ASX Announcement of 3 October 2023 for details of the most
recent MRE update.
During the Quarter further interpretation and targeting was undertaken on the HMS Sulphur host
unit as well as hanging wall and footwall stratigraphy that is geologically prospective but has been
subject to little previous effective exploration. This work is ongoing and, when completed, will be the
focus of follow-up drill testing
A review of the lithium potential of Mt McClure, including “bottom of hole” multi-element sampling
and analysis is ongoing.
GORDONS
The 100%-owned Gordons Project is located 35km north of Kalgoorlie. The project covers
approximately 52km2 of tenure adjacent to operating mines at Gordon Sirdar and Mulgarrie and is
close to both third party and publicly owned haulage infrastructure. Significantly, it is located on the
flank of the Scotia-Kanowna Dome, a key regional geological feature, that is an important control on
the formation of gold mineralisation, including the multi-million ounce Kanowna Belle and Paddington
deposits (see Figures 8 and 9).
During the Quarter the Company completed a comprehensive open file review and target generation
focussing on the Gordon Sirdar Shear Zone (GSSZ). The GSSZ extends through the Star of Gordon
prospect and Gordon-Sirdar Gold Mine, then to the immediate south of the Gordon Project towards
the +6.4Moz Kanowna Belle mine (ASX: NST). Importantly, it includes geological architecture
permissive for the formation of significant gold deposits, including stratigraphy interpreted to be the
same or equivalent to that at Kanowna Belle, and is therefore a high priority exploration target.
The Company is currently acquiring and reprocessing additional gravity data (initially public domain)
to assist in refining interpreted intrusion and paleochannel margins. Once completed, drilling targets
will be finalised with the intention of commencing drill testing priority targets in H1 2024, subject to
the grant of E26/701 and access approvals.
ASX Announcement 22 January 2024
Page 11
Figure 8: Gordons tenement plan showing location of the Gordons Project and major
prospects in relation to nearby mines
ASX Announcement 22 January 2024
Page 12
Figure 9: Gordons Project location map showing drill collars coloured by max Au
and the location of the Gordon Sirdar Shear Zone and splays over geology and the
approximate boundary of the heritage survey completed during the quarter.
ASX Announcement 22 January 2024
Page 13
LOOKING AHEAD
The Company has a very active Q1 2024 planned with priority exploration activities, including;
1. Follow-up exploration drilling including RC and diamond drilling across the Oblique Prospect
(IWB) scheduled to commence late March; this will include follow-up of some of the broad
intercepts obtained in the Phase 2 RC program, and testing for extensions and repeats of
the OB01 mineralised cross-cutting structure.
2.
Initial RC drill testing Quarter Moon (IWB) commencing March-April.
3. Completion of two deep (400m) diamond holes across the New England Granite Prospect
(IWB) to refine exploration targets for follow-up RC drilling across the 4.2km eastern granite
margin of the Prospect. Diamond drilling is assisted through EIS co-funding. Drilling is being
scheduled for March-April.
4. Assess results of the IWB orientation soil geochemical program testing for lithium and other
commodities and planning follow-up
5. Review the lithium potential of Mt McClure, including “bottom of hole” multi-element sampling
and analysis.
6. Finalisation of exploration targets and drilling strategy across the expanded Gordons Gold
Project, including acquisition of additional gravity data (initially public domain) and
reprocessing to better define intrusions and paleochannel margins.
CORPORATE SUMMARY
Capital Raising
During the quarter, the Company completed a placement raising $4m (before costs). The placement
was oversubscribed and strongly supported by major shareholders and had significant interest from
new investors with all directors participating in the placement. The 76.9m placement shares were
priced at $0.052 and included a 1-for-2 free attaching option with an exercise price of $0.11 and an
expiry date of 17 November 2025. In addition, 4m options were issued to MST Financial Services
Pty Ltd as sole lead manager to the placement.
Funds from the capital raising will be primarily focused on drilling, including Exploration Target testing
and Mineral Resource Estimate related activities at the Ironstone Well-Barwidgee, Mt McClure and
Gordons projects. Funds raised will also enable the acceleration of early-stage assessment for
lithium across the Yandal Belt tenements.
Issued Capital
Other than the securities issued pursuant to the capital raising completed during the quarter, the only
other movements in securities on issue during the quarter were the lapsing of 125,000 Class D
Performance Rights and 200,000 options with a 30 cent exercise price, and the issue of 2,700,000
options under the Company’s Employee Incentive Scheme.
ASX Announcement 22 January 2024
Page 14
As at 31 December 2023, the Company had the following securities on issue:
Type of Security
Number
Ordinary shares
234,726,156
Options
75,766,071
Performance rights
TOTAL
375,000
310,867,227
Summary of Exploration Expenditure
In accordance with Listing Rule 5.3.1, Yandal confirms that as disclosed in the Cashflow Report (item
1.2(a)), Yandal’s exploration expenditure for the quarter was approximately $1,032k, details of the
exploration activities underlying this expenditure are as set out in the Activities Report.
Payments to Related Parties and their Associates
In accordance with ASX Listing Rule 5.3.5, $172k was paid to related parties or their associates during
the quarter, comprising Executive Director salaries, Non-executive Director fees and superannuation.
The increase in this number over last quarter is primarily due to Exploration Manager, Chris Oorschot,
being appointed to the board as Technical Director early in the quarter, hence his salary is now
included in this figure.
Authorised by the board of Yandal Resources
For further information please contact:
Tim Kennedy
Managing Director
Yandal Resources Limited
yandal@yandalresources.com.au
ASX Announcement 22 January 2024
Greg Fitzgerald
Company Secretary
+61 8 9389 9021
cosec@yandalresources.com.au
Page 15
About Yandal Resources Limited
Yandal Resources listed on the ASX in December 2018 and has a portfolio of advanced gold exploration
projects in the highly prospective Yandal and Norseman-Wiluna Greenstone Belts of Western Australia.
Yandal Resources Ltd - Mineral Resource Summary
Deposit
Ironstone Well
Flushing Meadows1
Mt McClure
Challenger2
Success3
Parmelia4
HMS Sulphur5
Gilmore6
Sub-total - MMC
Gordons
Gordons Dam7
Grand-total8
Indicated
Tonnes Grade
(‘000s)
(g/t)
2,141
2,141
1.3
1.3
Au
(oz)
91,000
91,000
Inferred
Tonnes
Grade
(‘000)
(g/t)
Au
(oz)
Tonnes
(000’s)
Total
Grade
(g/t)
Au
(Oz)
5,245
1.1
177,000
7,386
1.1
268,000
718
1,255
252
1010
134
3,369
1.9
1.9
2.1
1.2
1.7
1.7
44,000
75,000
17,000
39,000
7,200
182,200
718
1,255
252
1010
134
3,369
1.9
1.9
2.1
1.2
1.7
1.7
44,000
75,000
17,000
39,000
7,200
182,200
365
8,979
1.7
1.3
20,000
379,200
365
11,120
1.7
1.4
20,000
470,200
Due to the effects of rounding, totals may not represent the sum of the individual components.
1. Reported above 0.5g/t Au lower cut-off grade; refer to Yandal Resources Ltd ASX announcement dated 4 November 2020 for
full details. 2. Reported above 1.0g/t Au lower cut-off grade; refer to Yandal Resources Ltd ASX announcement dated 22 August
2022 for full details 3. Reported above 1.0g/t Au lower cut-off grade; refer to Yandal Resources Ltd ASX announcement dated 6
September 2022 for full details.4. Reported above 1.0g/t Au lower cut-off grade; refer to Yandal Resources Ltd ASX announcement
dated 20 September 2022 for full details 5. Reported above 0.5g/t Au lower cut-off grade within this announcement 6. Reported
above 1.0g/t Au lower cut-off grade within this announcement 7. Reported above 1.0g/t Au lower cut-off grade; refer to Yandal
Resources Ltd ASX announcement dated 6 April 2023 for full details 8. All Resources are reported as global estimates, not
constrained by optimised pit shells.
Competent Person Statements
The information in this document that relates to Exploration Results, geology and data compilation is based
on information reviewed or compiled by Mr Christopher Oorschot, a Competent Person who is a Member
of The Australasian Institute Geoscientists. Mr Oorschot is the Exploration Manager for the Company, is
a full-time employee and holds options in the Company. Mr Oorschot has sufficient experience which is
relevant to the style of mineralisation and type of deposit under consideration and to the activity which he
is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code
for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Oorschot consents to the
inclusion in this announcement of the matters based on this information in the form and context in which it
appears.
The information in this announcement that relates to the Flushing Meadows, Mt McClure and Gordons
Dam Mineral Resource Estimates is based on information compiled and generated by Andrew Bewsher,
an employee of BM Geological Services Pty Ltd (“BMGS”). Both Andrew Bewsher and BMGS hold shares
in the company. BMGS consents to the inclusion, form and context of the relevant information herein as
derived from the original resource reports. Mr Bewsher has sufficient experience relevant to the style of
mineralization and type of deposit under consideration and to the activity which is being undertaken to
ASX Announcement 22 January 2024
Page 16
qualify as a Competent Person as defined in the 2012 Edition of the JORC ‘Australasian Code for
Reporting of Exploration Results, Mineral Resources and Ore Reserves’.
YRL confirms that it is not aware of any new information or data that materially affects the information
included in the original market announcements. The company confirms that the form and context in which
the Competent Person’s findings are presented have not been materially modified from the original market
announcement.
Forward Looking Statements
This document may contain certain forward-looking statements. Forward-looking statements include, but
are not limited to, statements concerning Yandal Resources Limited’s (Yandal’s) current expectations,
estimates and projections about the industry in which Yandal operates, and beliefs and assumptions
regarding Yandal’s future performance. When used in this document, words such as “anticipate”, “could”,
“plan”, “estimate”, “expects”, “seeks”, “intends”, “may”, “potential”, “should”, and similar expressions are
forward-looking statements. Although Yandal believes that its expectations reflected in these forwardlooking statements are reasonable, such statements are subject to known and unknown risks,
uncertainties and other factors, some of which are beyond the control of Yandal and no assurance can be
given that actual results will be consistent with these forward-looking statements. Drilling results presented
indicate geological potential for mineralisation but there can be no certainty that these results will
eventually form part of a Mineral Resource Estimate.
ASX Announcement 22 January 2024
Page 17
Tenement Schedule as at 31 December 2023
Interest
acquired
during
the
Quarter
Interest
disposed
during the
Quarter
Tenement ID
Status
Holder
Ownership
at Quarter
End
Oblique/Quarter Moon
E53/1882
Granted
Yandal
100%
-
-
Flushing Meadows
E53/1963
Granted
Yandal
100%
-
-
Wiluna
ELA53/2191
Application
Legendre
100%
-
-
1
Wiluna
ELA53/2192
Application
Legendre
100%
-
-
1
Wiluna
ELA53/2193
Application
Legendre
100%
-
-
1
Wiluna
ELA53/2194
Application
Legendre
100%
-
-
1
Flushing Meadows Haul Rd
LA53/222
Application
Yandal
100%
-
-
Locality
Notes
Ironstone Well Gold Project
Ironstone Well
M53/1093
Granted
Yandal
100%
-
Flushing Meadows
MLA53/1108
Application
Yandal
100%
-
-
Newcombe
ELA53/2304
Application
Yandal
100%
-
-
New England
E53/1843
Granted
Yandal
100%
-
-
New England
P53/1638
Granted
Yandal
100%
-
-
New England
P53/1639
Granted
Yandal
100%
-
-
Mazzucco
P53/1704
Granted
Yandal
100%
-
-
Greenstone Hill
P53/1714
Granted
Yandal
100%
-
-
Greenstone Hill
P53/1715
Granted
Yandal
100%
-
-
Success
M36/691
Granted
Yandal
100%
-
-
Parmelia
M36/692
Granted
Yandal
100%
-
-
Challenger
M36/693
Granted
Yandal
100%
-
-
Mt McClure
P36/1892
Granted
Yandal
100%
-
-
Mt McClure
P36/1893
Granted
Yandal
100%
-
-
Mt McClure
P36/1894
Granted
Yandal
100%
-
-
Mt McClure
P36/1895
Granted
Yandal
100%
-
-
Mt McClure
P36/1896
Granted
Yandal
100%
-
-
Success
P36/1922
Granted
Yandal
100%
-
-
Mt McClure
P36/1934
Granted
Yandal
100%
-
-
Mt McClure
P36/1935
Granted
Yandal
100%
-
-
Mt McClure
P36/1936
Granted
Yandal
100%
-
-
Mt McClure
P36/1937
Granted
Yandal
100%
-
-
Mt McClure
P36/1938
Granted
Yandal
100%
-
-
Mt McClure
P36/1939
Granted
Yandal
100%
-
-
Mt McClure
P36/1940
Granted
Yandal
100%
-
-
Barwidgee Gold Project
Mt McClure Gold Project
Mt McClure
P36/1941
Granted
Yandal
100%
-
Mt McClure
P36/1942
Granted
Yandal
100%
-
-
Mt McClure
P36/1943
Granted
Yandal
100%
-
-
Mt McClure
P36/1944
Granted
Yandal
100%
-
-
Mt McClure
P36/1945
Granted
Yandal
100%
-
-
Mt McClure
P36/1946
Granted
Yandal
100%
-
-
Gordons Gold Project
ASX Announcement 22 January 2024
Page 18
Tenement Schedule as at 31 December 2023
Int