SEPTEMBER 2025 - QUARTERLY ACTIVITIES REPORT
KEY POINTS
Caladan Target Area
• Arrakis discovery confirmed with RC drilling returning several significant fresh rock
intercepts below a 2.2km long mineralised structure defined by air-core drilling, including:
o 54m*1 @ 1.2g/t Au from 108m to EOH in 25IWBRC0040, including
24m @ 2.1g/t Au from 138m to EOH. This interval further includes:
• 8m @ 4.7g/t Au from 154m to EOH.
o 50*1m @ 1.3g/t Au from 122m in 25IWBRC0042, including
28m @ 1.9g/t Au from 143m. This interval further includes:
• 9m @ 2.1g/t Au from 145m, and
• 7m @ 2.7g/t Au from 164m.
*1: Down-hole width reported, as true width is uncertain, and further drilling is required to confirm the geometry of
mineralisation.
New England Granite
• Air-core drilling completed across the New England Granite, testing new structural
targets across the larger-scale intrusive.
Corporate
• Approx. $2.26m in cash and cash equivalents available at the end of the
Quarter.
• Capital Raise completed subsequent to quarter end, securing $13.5m (before
costs) in funding to advance and accelerate exploration across the recent
Arrakis discovery, New England Granite target area and the Flushing Meadows
deposit.
• A binding tenement sale agreement was executed with Horizon Minerals Limited
(ASX: HRZ) for the sale of the Gordons Gold Project for a total consideration of
A$2.81m in cash and HRZ shares.
• As at quarter end, there were 23.9m unlisted YRL options with an exercise price of
$0.11 expiring at 5:00pm (WST) on Monday, 17 November 2025. The total
proceeds to be received from these options, if exercised, is A$2.6m. The Board
notes these Options are currently “in the money”.
ASX Announcement
29 October 2025
For further information or to ask questions in relation to this announcement, please visit our
Investor Hub at https://yandalresources.com.au/link/P2zq2P
yandalresources.com.au | ASX:YRL 2
Yandal Resources Ltd (ASX: YRL, “Yandal Resources” or the “Company”) is pleased to provide a
summary of operational and corporate activities undertaken during the Quarter ended 30
September 2025.
The Company remains focused on exploring its portfolio of highly prospective 100% owned gold
projects located within the Yandal Greenstone Belt in Western Australia (Figure 1).
Figure 1: Yandal Resources’ gold project locations.
250 Kilometres
N
IRONSTONE WELL–BARWIDGEE
GOLD PROJECT
MOUNT McCLURE
GOLD PROJECT
WESTERN
AUSTRALIA
yandalresources.com.au | ASX:YRL 3
September Quarter Operational Summary and 2025/2026 Outlook
The September 2025 Quarter saw the confirmation of the Company's second new discovery
within twelve months, demonstrating the capacity of the Yandal Greenstone Belt to yield new
discoveries and further validating the Company's exploration strategy and methodology.
During the Quarter the operational focus was centred on completing the 13,500m air-core
program across the Caladan target area. Results received from the air-core program defined
the 2.2km long Arrakis mineralised trend. RC drilling was then completed, testing below a number
of air-core intercepts that defined the Arrakis trend. The RC results confirmed significant fresh rock
mineralisation, solidifying Arrakis as a new gold discovery and demonstrating the potential for a
large-scale mineralised system.
Across the New England Granite target area, the first half of the New England Granite air-core
program was completed, with 13 holes totalling 1,400m completed. The program was paused for
the follow-up RC drilling at Arrakis and has since recommenced in October.
At the Mt McClure Gold Project, a ground gravity survey was completed across the entire project
to aid in stratigraphic and structural interpretations. These interpretations will support future
targeting and exploration drilling.
Looking ahead, the Company will continue to aggressively advance exploration across both the
recent Arrakis discovery and the broader Caladan target area, with a focus on defining the
extents of the newly identified mineralised system. Across the New England Granite, results from
the ongoing air-core program will provide follow-up RC drilling targets in 2026. The Company is
also looking to develop an exploration strategy for the Flushing Meadows deposit that focuses
on understanding the distribution of fresh rock mineralisation and testing parallel targets.
yandalresources.com.au | ASX:YRL 4
IRONSTONE WELL-BARWIDGEE
The 100% owned Ironstone Well-
Barwidgee (IWB) Gold Project
covers approximately 370km² of
highly prospective and under-
explored tenure located between
the Jundee and Bronzewing mines
in the northern Yandal Greenstone
Belt (Figure 2).
Yandal has an established
Resource of 268,000oz of gold at
Flushing Meadows and considers
there to be strong potential to
make new discoveries and
expand this resource base within its
extensive tenure holding. (Refer to the
ASX announcement of 4 November 2020 for details of
the Flushing Meadows Resource)
The IWB project area includes two
new gold discoveries, the Arrakis
and Siona Prospects, both made
within the last twelve months and
following the execution of a
revised targeting and exploration
strategy developed in early 2023.
Both discoveries are currently at
an early stage, with future activities focused on delineating the scale of each of the newly
defined mineralised systems. The IWB Gold Project also includes several advanced
prospects, where limited historic and YRL drilling has returned robust gold intercepts,
indicating the potential for shallow oxide mineralisation. Both the early-stage and more
advanced prospects are the focus of ongoing exploration.
The recent discoveries include the Arrakis prospect hosted within the Caladan fold and the
Siona prospect hosted within the New England Granite.
Caladan Target Area
In June 2024, a series of new high-priority targets were identified based on detailed gravity
data collected by Yandal and a comprehensive analysis of open-file data. Most notable
was the identification of the Caladan target area (see Figure 2), which shows broad
geological similarities to several world-class gold camps (see ASX Release 11 June 2024),
including:
Figure 2: Simplified geology plan across the IWB Gold Project showing
active prospects and exploration target areas, including the Siona
and Arrakis Prospects.
Caladan
Target Area
Irulan Dolerite
Complex
New England
Granite
Siona
Arrakis
Discovery
Flushing Meadows
(268Koz)
Oblique
Quarter
Moon
Salusa
yandalresources.com.au | ASX:YRL 5
• The interpreted Caladan Fold displays similarities to the broader structural setting of
the Boomerang Anticline that hosts the Golden Mile Deposit; and
• The folded mafic sequence of the Timmins-Porcupine gold district in Canada.
Across the Caladan target area, several low-level in-situ saprolite anomalies were
identified within shallow historical drilling, including a continuous 3km long northwest
striking anomaly within the core of the interpreted Caladan Fold designated CAL-01 (now
the Arrakis Prospect). Significantly, this broad-spaced drilling was shallow and only tested
upper saprolite clays; a portion of the regolith profile prone to gold depletion across the
Yandal Greenstone Belt. The regolith anomaly, combined with the structural setting, and
the untested nature of this large target area, emphasised the need for more effective
exploration across the newly defined structural setting.
In October 2024 a single line of air-core drilling was completed across the core of the
Caladan target area, testing the central part of the CAL-01 anomaly (Arrakis Trend), with
follow-up RC drilling completed in the March Quarter of 2025. Air-core drilling across the
core of the Caladan fold returned:
o 11m @ 1.7 g/t Au from 97m to end-of-hole in 24IWBAC063,
including 3m @ 3.5 g/t Au from 102m.
RC drilling indicated potential for mineralisation continuity into fresh rock and a potential
sub-vertical geometry.
Caladan Air-Core Drilling
In early June of 2025, the large-scale Caladan AC program commenced. The program saw
drilling across ten lines, with a total of 132 holes for 13,458m of drilling completed during the
Quarter. The air-core program tested a significant expanse of the Caladan target area, including
6.4km of strike (See Figure 6).
Results from the air-core program were reported in July and August (see ASX releases 10 July 2025,
31 July 2025, and 8 August 2025). The results defined the more than 2.2km mineralised Arrakis
trend based on significant intercepts, including:
o 11m @ 2.1 g/t Au from 90m in 25IWBAC023, including
7m @ 3.1 g/t Au from 92m.
o 12m @ 1.1g/t Au from 45m in 25IWBAC032, including
2m @ 3.2g/t Au from 45m and,
1m @ 2.5g/t Au from 53m.
o 12m @ 0.5g/t from 70m to EOH in 25IWBAC032, including
yandalresources.com.au | ASX:YRL 6
1m @ 2.0g/t Au from 74m.
o 11m @ 1.4 g/t Au from 71m in 25IWBAC044, including
6m @ 2.3 g/t Au from 72m,
o 1m @ 1.0g/t Au from 87m to EOH in 25IWBAC044
Arrakis RC Drilling
In early September, a targeted seven-hole RC program commenced across Arrakis, testing
below air-core intercepts that defined the more than 2.2km mineralised trend (see Figure 3) to
confirm mineralisation continuity in fresh rock and assess the geometry of mineralisation.
RC drilling successfully confirmed primary fresh rock mineralisation (see Figures 4 & 5) with
intercepts including:
o 54m*1 @ 1.2g/t Au from 108m to EOH in 25IWBRC0040, including
24m @ 2.1g/t Au from 138m to EOH. This interval further includes:
• 8m @ 4.7g/t Au from 154m to EOH.
o 50*1m @ 1.3g/t Au from 122m in 25IWBRC0042 (ETW of 24m), including
28m @ 1.9g/t Au from 143m. This interval further includes:
• 9m @ 2.1g/t Au from 145m, and
• 7m @ 2.7g/t Au from 164m.
*1: Down-hole width reported, as true width is uncertain, and further drilling is required to confirm the geometry of
mineralisation.
Several RC holes ended in mineralisation or were unable to reach the designed depth. These
holes will be extended with a diamond tail as part of the diamond drilling program that is currently
underway.
Defining the Arrakis Mineralised System
A 2,000m diamond drilling program is underway, having commenced earlier in October (see ASX
release 13 October 2025). The program will see the completion of several diamond tails,
extending RC holes that either ended in mineralisation or did not reach the designed target. In
addition, diamond drilling from surface will be completed below the recently reported intercepts
(see Figure 4).
Two heritage surveys completed in September and October will provide both 200m and 100m-
spaced drill lines across the more than 2.2km Arrakis trend. RC drilling scheduled to commence
in mid-November will look to map out the extent of mineralisation across the 200m spaced drill
lines (see Figure 6). The RC program will enable the exploration team to assess the scale of the
mineralised system in preparation for further RC drilling in 2026.
yandalresources.com.au | ASX:YRL 7
Further air-core drilling across the broader Caladan target area is also scheduled; this drilling will
look to test along-strike of the current Arrakis trend, along with several parallel regolith anomalies
(see Figure 6). The Air-core drilling will be completed over the coming months and into 2026.
Figure 3: A collar plan over the Arrakis Prospect within the Caladan target area, showing simplified
bedrock geology interpretation. All Yandal drilling is plotted (historic drilling has been excluded.
Collars are thematically coloured by max Au (g/t) in the hole. The red line represents the approximate
position of the interpreted Arrakis mineralised structure. Dashed yellow polygons represent air-core
regolith anomalies (Results include ~4m @ 0.1 g/t Au or greater, with the upper profile or the bottom-
of-hole sample is 0.1g/t Au or greater).
Interpreted
Arrakis
Structure
11m @ 1.7g/t to EOH
5m @ 0.7g/t Au
from 112m to EOH
22m @ 0.4 g/t Au
Incl. 7m @ 1.2 g/t Au
12m @ 1.1 g/t Au &
12m @ 0.5 g/t Au to EOH
11m @ 2.1g/t Au 25IWBRC0041
6m @ 1.1 g/t Au to EOH
25IWBRC0040
54m @ 1.2 g/t Au incl.
24m @ 2.1 g/t Au to EOH
25IWBRC0042
50m @ 1.3 g/t Au incl.
28m @ 1.9g/t Au
25IWBRC0043
16m @ 1.1 g/t Au
25IWBRC0046
To be extended
25IWBRC0044
To be extended
25IWBRC0045 - NSA
yandalresources.com.au | ASX:YRL 8
Figure 4: Cross-section showing all RC drilling results from 25IWBRC0040 and 25IWBRC0041, with
a simple preliminary interpretation of geology. The section location is shown in Figure 3. The
section shows all drilling within +/- 50m of the section plane. The dark blue line represents planned
diamond core drilling, including a diamond tail extending 25IWBRC0041 with diamond drilling.
Cross-Section B
northwest facing
Transported Cover
Surface
Dolerite
11m @ 1.4 g/t Au
incl. 6m @ 2.3 g/t Au
6m @ 1.1 g/t Au to EOH
Regolith
Anomalies
54m @ 1.2 g/t Au incl.
24m @ 2.1 g/t Au to EOH
Planned
Diamond
Tail
Planned
Diamond
Drill Hole
RC EOH 186m
yandalresources.com.au | ASX:YRL 9
Figure 5: Cross-section showing all RC drilling results from 25IWBRC0042 and 25IWBRC0043, with
a simple preliminary interpretation of geology. The section location is shown in Figure 2. The
section shows all drilling within +/- 50m of the section plane. Please note the plan view at top of
section and the 30m offset between intercepts within the two reported RC holes.
Arrakis Cross-Section B
northwest facing
Transported Cover
Surface
Dolerite
12m @ 0.5 g/t Au
6m @ 0.3 g/t Au
50m @ 1.3 g/t Au incl.
28m @ 1.9 g/t Au
16m @ 0.7g/t Au
Basalt
Plan View
Regolith
Anomalies
12m @ 1.1 g/t Au
6m @ 0.8 g/t Au
Surface Projection of
Arrakis Mineralisation
yandalresources.com.au | ASX:YRL 10
Figure 6: A collar plan over the Caladan target area, which hosts the Arrakis Discovery, showing
simplified bedrock geology interpretation. All effective drilling is plotted (>20m down-hole
depth). Collars are thematically coloured by max Au (g/t) in the hole. The red line represents the
approximate position of the interpreted Arrakis mineralised structure. Dashed yellow polygons
represent air-core regolith anomalies (Results include ~4m @ 0.1 g/t Au or greater, with the upper
profile or the bottom-of-hole sample is 0.1g/t Au or greater). Purple lines represent cleared drill
lines following a heritage survey completed in August, including 200m space lines that will be
cleared in preparation for RC drilling in November.
Caladan
Fold
Interpreted Arrakis
Structure
25IWBRC0041
6m @ 1.1 g/t Au to EOH
25IWBRC0042
50m @ 1.3 g/t Au incl.
28m @ 1.9g/t Au
25IWBRC0043
16m @ 1.1 g/t Au
25IWBRC0040
54m @ 1.2 g/t Au incl.
24m @ 2.1 g/t Au to EOH
25IWBRC0046
To be extended
25IWBRC0044
To be extended
25IWBRC0045 - NSA
yandalresources.com.au | ASX:YRL 11
New England Granite
The New England Granite target area (see Figure 2) comprises a 4.2km long, 2km wide
granitoid, covered by 6-20m of transported cover that exhibits strong regolith gold
anomalism in shallow historical drilling proximal to the eastern contact. In October 2024, the
Siona discovery was made (see ASX release dated 21 October 2024), demonstrating the
capacity of the large intrusive body to host significant mineralisation. Since the discovery,
the Company has focused on understanding the scale of the Siona Discovery and targeting
similar positions across the expansive host.
Refining Structural Targets
The completion of diamond drilling earlier in 2025 has allowed a detailed set of geological
observations to be made and analysed. The most significant observation made by Yandal
Resources is that mineralisation develops wherever deformation occurs, both proximal and distal
to the host intrusive margin. This observation was reinforced by the RC exploration drilling program
completed across the Salusa Prospect on the southeast corner of the New England Granite (see
ASX release 15 April 2025), including:
o 2m @ 9.4g/t Au from 33m in 25IWBRC0019, and
o 14m @ 0.8g/t Au from 82m in 25IWBRC0019
The geological observations highlight the suitability of the granodiorite as a host for gold
mineralisation. It allows the development of a simple set of targeting criteria to prioritise structural
targets derived from geophysics. With the receipt of all diamond drilling results earlier in 2025, the
targeting criteria for the New England Granite have been revised to include:
- Targeting structures that interact with the intrusive margin with observable offsets (lateral or
vertical);
- Prioritise northwest-trending features and northeast-striking conjugate structures of a similar
relative age within the intrusive away from the intrusive margin;
- Prioritise structures that are oblique to the granodiorite margin.
In addition to the above, the concept of gold mineralisation occurring deep into the intrusive
away from the intrusive contact is yet to be adequately tested. Figure 7 shows the priority
structural targets that will be the focus of air-core drilling in 2025.
During the Quarter, a 5,000m air-core program commenced. The program was designed to
broadly test recently identified structural targets across the southern and western margin of the
New England Granite. During the Quarter, the program was paused to complete the follow-up
RC drilling at Arrakis and has since recommenced following the end of September.
yandalresources.com.au | ASX:YRL 12
Figure 7: Plan showing processed infill ground gravity dataset (BA267 1VD northwest
shade linear colour scale) across the New England Granite area. The plan includes
the updated interpretation of the intrusive margin and a preliminary interpretation of
structures interacting with the intrusion. Broad structural targets include Salusa and
NEG01-NEG04.
yandalresources.com.au | ASX:YRL 13
Flushing Meadows
The Flushing Meadows deposit hosts a 268koz @ 1.1g/t Mineral Resource Estimate (see ASX
release 4 November 2020) with mineralisation occurring over 1.9km of strike and is located
approximately 8km west-northwest of the Arrakis discovery (see Figure 2). A majority of
previous drilling was completed to define the predominantly oxide and transition gold
mineralisation, with minimal fresh rock drilling below the Mineral Resource.
Regional soil sampling and ground gravity surveys have highlighted several targets either
along strike or parallel to the currently defined extent of mineralisation at Flushing Meadows
(see Figure 8). Heritage surveys are currently being scheduled for either the end of 2025 or
early in 2026. A program of air-core, RC, and diamond drilling is being designed for
exploration in 2026.
Figure 8: A collar plan over the Flushing Meadows deposit, showing simplified bedrock
geology interpretation. All effective drilling is plotted (>20m down-hole depth). Collars are
thematically coloured by max Au (g/t) in the hole.
Flushing Meadows
Soil Anomaly
Flushing
Meadows
268koz MRE
Geidi Prime
Target
yandalresources.com.au | ASX:YRL 14
Mt McClure
The Mt McClure Gold Project is located 15km south-west of the historic Bronzewing gold
mine and 10km from the Orelia gold mine (see Figure 9), both owned by Northern Star
Resources Ltd (ASX: NST) in the southern Yandal Greenstone Belt (see Figure 1). The project
covers a total strike length of 17km of prospective stratigraphy and includes several shallow
historical open-cut pits.
The Mt McClure Mineral Resource Inventory is 182,200oz @ 1.7 g/t Au, all located on granted
mining leases.
The project has prospectivity for new shallow gold deposits adjacent to current Resources
and in the footwall and hanging wall of the stratigraphy. The Company completed a
ground gravity survey in the September Quarter to support revised structural and
stratigraphic interpretations and enhance targeting for work scheduled in 2026.
yandalresources.com.au | ASX:YRL 15
Figure 9: Mt McClure tenement plan showing the location of major prospects,
interpreted bedrock lithology, major structures and proximity to nearby mines.
yandalresources.com.au | ASX:YRL 16
GORDONS
During the Quarter, a binding tenement sale agreement was executed with Horizon Minerals
Limited (ASX: HRZ) for the sale of the Gordons Gold Project. The sale agreement for the
Company’s 100% interest in the Gordons Gold Project was executed for a total consideration
payable to Yandal by Horizon under the Agreement of A$2.81m on the following terms:
• A$0.2m refundable cash deposit on execution of the TSA (paid)
• A$1.0m cash (cash payment) on completion, and,
• A$1.610m in fully paid ordinary Horizon shares (“Consideration Shares”) on
completion. The Consideration Shares are not subject to any escrow restrictions.
Horizon may, however, at its sole election at completion, pay the A$1.610m in cash
in lieu of the Consideration Shares.
The tenement sale agreement follows a strategic review completed in the March quarter,
which recommended the sale of non-core assets, including the Gordons Gold Project,
allowing the Company to focus on exploration activities across the IWB Gold Project and
fund exploration. KPMG Corporate Finance advised on and managed the divestment of the
Gordons Gold Project.
yandalresources.com.au | ASX:YRL 17
LOOKING AHEAD
The Company has a very active December Quarter scheduled. Notable near-term
activities and potential news flow include;
1. Diamond drilling underway at Arrakis including several re-entries of RC holes extending
drilling through the interpreted Arrakis structure, and several new holes completed
below recent RC intercepts;
2. AC drilling program across the New England Granite is nearing completion, with results
from the first half of the program anticipated in the coming weeks;
3. Further RC drilling on 200m spaced lines across the Arrakis discovery scheduled for mid-
November, to define the extent of the newly identified mineralised system;
4. Completion of the Gordons Gold Project Tenement Sale Agreement for total
consideration of A$2.81m is expected shortly; and
5. 23.6m unlisted YRL options with an exercise price of $0.11 will expire at 5:00pm (WST) on
Monday, 17 November 2025. The total value of these options if exercised is A$2.6m.
CORPORATE SUMMARY
Issued Capital
The movements in securities on issue during the quarter were as follows:
• issue of 1,550,000 options pursuant to the Company’s Employee Incentive Securities
Plan; and
• lapsing of 150,000 options previously issued under the Company’s Employee Incentive
Securities Plan.
The securities on issue at the start and end of the quarter are summarised in the table below.
Type of Security 30 June 2025 Movement in
September Qtr
30 September
2025
Ordinary shares 309,234,982 - 309,234,982
Options 11c 17/11/25 expiry 23,888,703 - 23,888,703
Options - other 14,200,000 1,400,000 15,600,000
TOTAL 347,323,685 1,400,000 348,723,685
Subsequent to Quarter End
Subsequent to quarter end, Yandal issued 46,385,247 new shares at an issue price of 29 cents
each to raise $13.5m before costs. A further 265,385 new shares were issued on 8 October
2025 as a result of options with an 11 cent strike price being exercised. The securities on issue
at the date of this report are:
yandalresources.com.au | ASX:YRL 18
Type of Security 29 October 2025
Ordinary shares 355,885,614
Options 11c 17/11/25 expiry 23,623,318
Options - other 15,600,000
TOTAL 395,108,932
Summary of Exploration Expenditure
In accordance with Listing Rule 5.3.1, Yandal confirms that as disclosed in the Cashflow
Report (item 1.2(a)), Yandal’s exploration expenditure for the quarter was approximately
$2.12 million details of the exploration activities underlying this expenditure are as set out in
the Activities Report.
Payments to Related Parties and their Associates
In accordance with ASX Listing Rule 5.3.5, $111k was paid to related parties or their associates
during the quarter, comprising Executive Director salaries, Non-executive Director fees and
superannuation.
Authorised by the board of Yandal Resources
For further information, please contact:
Chris Oorschot
Managing Director
Yandal Resources Limited
yandal@yandalresources.com.au
Greg Fitzgerald
Company Secretary
+61 8 9389 9021
yandal@yandalresources.com.au
About Yandal Resources Limited
yandalresources.com.au | ASX:YRL 19
About Yandal Resources Limited
Yandal Resources Limited (ASX: YRL) is an ASX-listed gold explorer company which has a portfolio of
advanced gold exploration projects in the highly prospective Yandal and Norseman-Wiluna Greenstone
Belts of Western Australia. These Gold Projects include the Gordons, Mt McClure and Ironstone Well-
Barwidgee.
Table 1: Yandal Resources Ltd - Mineral Resource Summary
Deposit
Indicated Inferred Total
Tonnes
(‘000s)
Grade
(g/t)
Au
(oz)
Tonnes
(‘000)
Grade
(g/t)
Au
(oz)
Tonnes
(000’s)
Grade
(g/t)
Au
(Oz)
Ironstone Well
Flushing Meadows1 2,141 1.3 91,000 5,245 1.1 177,000 7,386 1.1 268,000
Mt McClure
Challenger2 718 1.9 44,000 718 1.9 44,000
Success3 1,255 1.9 75,000 1,255 1.9 75,000
Parmelia4 252 2.1 17,000 252 2.1 17,000
HMS Sulphur5 1010 1.2 39,000 1010 1.2 39,000
Gilmore6 134 1.7 7,200 134 1.7 7,200
Sub-total - MMC 3,369 1.7 182,200 3,369 1.7 182,200
Gordons
Gordons Dam7 365 1.7 20,000 365 1.7 20,000
Grand-total8 2,141 1.3 91,000 8,979 1.3 379,200 11,120 1.4 470,200
Due to the effects of rounding, totals may not represent the sum of the individual
components.
1. Reported above 0.5g/t Au lower cut-off grade; refer to Yandal Resources Ltd ASX announcement dated 4 November
2020 for full details. 2. Reported above 1.0g/t Au lower cut-off grade; refer to Yandal Resources Ltd ASX announcement
dated 22 August 2022 for full details 3. Reported above 1.0g/t Au lower cut-off grade; refer to Yandal Resources Ltd ASX
announcement dated 6 September 2022 for full details.4. Reported above 1.0g/t Au lower cut-off grade; refer to Yandal
Resources Ltd ASX announcement dated 20 September 2022 for full details 5. Reported above 0.5g/t Au lower cut-off
grade within this announcement 6. Reported above 1.0g/t Au lower cut-off grade within this announcement 7. Reported
above 1.0g/t Au lower cut-off grade; refer to Yandal Resources Ltd ASX announcement dated 6 April 2023 for full details
8. All Resources are reported as global estimates, not constrained by optimised pit shells.
Competent Person Statement
The information in this document related to Exploration Targets and Exploration Results, geology
and data compilation is based on information reviewed or compiled by Mr Christopher Oorschot,
a Competent Person who is a Member of The Australasian Institute Geoscientists. Mr Oorschot is
the Managing Director for the Company, is a full-time employee and holds shares and options in
the Company. Mr Oorschot has sufficient experience which is relevant to the style of
mineralisation and type of deposit under consideration and to the activity which he is
undertaking to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Oorschot
consents to the inclusion in this announcement of the matters based on this information in the
form and context in which it appears.
The information in this announcement that relates to the Flushing Meadows, Mt McClure and
Gordons Dam Mineral Resource Estimates is based on information compiled and generated by
Andrew Bewsher, an employee of BM Geological Services Pty Ltd (“BMGS”). Both Andrew
Bewsher and BMGS hold shares in the company. BMGS consents to the inclusion, form and
context of the relevant information herein as derived from the original resource reports. Mr
yandalresources.com.au | ASX:YRL 20
Bewsher has sufficient experience relevant to the style of mineralisation and type of deposit under
consideration and to the activity which is being undertaken to qualify as a Competent Person as
defined in the 2012 Edition of the JORC ‘Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves’.
YRL confirms that it is not aware of any new information or data that materially affects the
information included in the original market announcement. The Company confirms that the form
and context in which the Competent Person’s findings are presented have not been materially
modified from the original market announcement.
Forward Looking Statements
This document may contain certain forward-looking statements. Forward-looking statements
include, but are not limited to, statements concerning Yandal Resources Limited’s (Yandal’s)
current expectations, estimates and projections about the industry in which Yandal operates,
and beliefs and assumptions regarding Yandal’s future performance. When used in this
document, words such as “anticipate”, “could”, “plan”, “estimate”, “expects”, “seeks”,
“intends”, “may”, “potential”, “should”, and similar expressions are forward-looking statements.
Although Yandal believes that its expectations reflected in these forward-looking statements are
reasonable, such statements are subject to known and unknown risks, uncertainties and other
factors, some of which are beyond the control of Yandal and no assurance can be given that
actual results will be consistent with these forward-looking statements. Drilling results presented
indicate geological potential for mineralisation but there can be no certainty that these results
will eventually form part of a Mineral Resource Estimate.
yandalresources.com.au | ASX:YRL 21
Tenement Schedule as at 30 September 2025
Locality Tenement ID Status Holder
Ownership
at Quarter
End
Interest
acquired
during
the
Quarter
Interest
disposed
during the
Quarter
Notes
Ironstone Well Gold Project
Oblique/Quarter Moon E53/1882 Granted Yandal 100% - -
Flushing Meadows E53/1963 Granted Yandal 100% - -
Wiluna E53/2191 Granted Legendre 100% - -
Wiluna E53/2192 Granted L